Common use of Work Progress Clause in Contracts

Work Progress. The DeveloperInterconnection Customer and Connecting Transmission Owner will keep each other, and NYISO, advised periodically as to the progress of their respective design, procurement and construction efforts. Any Party may, at any time, request a progress report from the DeveloperInterconnection Customer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- Service Date, the DeveloperInterconnection Customer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 3 contracts

Sources: Standard Large Generator Interconnection Agreement, Service Agreement, Sithe Interconnection Agreement

Work Progress. The DeveloperInterconnection Customer Transmission Developer and Connecting Transmission Owner will keep each other, and NYISO, advised periodically as to the progress of their respective design, procurement and construction effortsefforts of the Transmission Project and the Network Upgrade Facilities. Any Party may, at any time, request a progress report from the DeveloperInterconnection Customer Transmission Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 3 contracts

Sources: Service Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Work Progress. The DeveloperInterconnection Customer Developer and Connecting Transmission Owner will keep each other, ,the Affected System Operator and NYISO, advised periodically as to the progress of their theirits respective design, procurement and construction efforts. Any Party PartyAffected System Operator or NYISO may, at any time, request a progress report from the DeveloperInterconnection Customer Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required...

Appears in 2 contracts

Sources: Standard Large Generator Interconnection Service Agreement, Engineering, Procurement, and Construction Agreement

Work Progress. The DeveloperInterconnection Customer Developer and Connecting ConnectingAffected Transmission Owner will keep each eachthe other, and NYISO, Parties advised periodically as to the progress of their respective respectiveits design, procurement and construction efforts. Any Party may, at any time, request a progress report from the DeveloperInterconnection Customer Developer or Connecting ConnectingAffected Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 2 contracts

Sources: Engineering, Procurement, and Construction Agreement, Engineering, Procurement, and Construction Agreement

Work Progress. The DeveloperInterconnection Customer DeveloperAffected System Operator and Connecting Transmission Owner will keep each other, ,the Developer and NYISO, advised periodically as to the progress of their respective design, procurement and construction efforts. Any Party PartyDeveloper or NYISO may, at any time, request a progress report from the DeveloperInterconnection Customer DeveloperAffected System Operator or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 1 contract

Sources: Engineering, Procurement, and Construction Agreement

Work Progress. The DeveloperInterconnection Customer Transmission Developer and Connecting Transmission Owner will keep each other, and NYISO, advised periodically as to the progress of their respective design, procurement and construction effortsefforts of the NYPA Transmission Facilities and the Network Upgrade Facilities. Any Party may, at any time, request a progress report from the DeveloperInterconnection Customer Transmission Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement

Work Progress. The DeveloperInterconnection Customer Developer and Connecting Transmission Owner will keep each other, ,the Affected System Operator and NYISO, advised periodically as to the progress of their theirits respective design, procurement and construction efforts. Any Party PartyAffected System Operator or NYISO may, at any time, request a progress report from the DeveloperInterconnection Customer Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.Developer.

Appears in 1 contract

Sources: Engineering, Procurement, and Construction Agreement

Work Progress. The DeveloperInterconnection Customer Transmission Developer and Connecting Transmission Owner will keep each other, ,the Affected System Operator and NYISO, advised periodically as to the progress of their respective respectiveits design, procurement and construction efforts. Any Party PartyAffected System Operator or NYISO may, at any time, request a progress report from the DeveloperInterconnection Customer Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.Transmission Developer.

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement

Work Progress. The DeveloperInterconnection Customer Developer and Connecting Transmission Owner will keep each other, ,the Transmission Developer and NYISO, advised periodically as to the progress of their respective respectiveits design, procurement and construction efforts. Any Party PartyThe Transmission Developer or NYISO may, at any time, request a progress report from the DeveloperInterconnection Customer Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement

Work Progress. The DeveloperInterconnection Customer Developer and Connecting Transmission Owner will keep each other, ,the Affected System Operator and NYISO, advised periodically as to the progress of their theirits respective design, procurement and construction efforts. Any Party PartyAffected System Operator or NYISO may, at any time, request a progress report from the DeveloperInterconnection Customer Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.Developer.

Appears in 1 contract

Sources: Engineering, Procurement, and Construction Agreement

Work Progress. The DeveloperInterconnection Customer Interconnection CustomerThe Developer and Connecting Transmission Owner will keep each other, and NYISO, advised periodically as to the progress of their respective design, procurement and construction efforts. Any Party may, at any time, request a progress report from the DeveloperInterconnection Customer Interconnection Customerthe Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Interconnection Customerthe Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- Initial FeedbackIn-Service Date, the DeveloperInterconnection Customer Interconnection Customerthe Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 1 contract

Sources: Class Year Cluster Study Agreement

Work Progress. The DeveloperInterconnection Customer Transmission Developer and Connecting Transmission Owner will keep each other, and the NYISO, advised periodically as to the progress of their respective design, procurement and construction effortsefforts of the Transmission Project and the Network Upgrade Facilities. Any Party may, at any time, request a progress report from the DeveloperInterconnection Customer Transmission Developer or Connecting Transmission Owner. If, at any time, the DeveloperInterconnection Customer Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In- In-Service Date, the DeveloperInterconnection Customer Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement