Common use of Witness and Hold Points Clause in Contracts

Witness and Hold Points. (a) Following the selection of a specific vendor for Equipment identified in Exhibit Q that is part of the Standard Plant and for which there are contractual Witness Points and Hold Points, Contractor shall identify the associated Witness Points and Hold Points via inclusion of the Witness Points and Hold Points in the manufacturing and fabrication plans for the Equipment. After review, Owner may identify additional Witness Points and Hold Points and Owner shall notify Contractor of any Owner-designated Witness Points or Hold Points that they shall attend. In cases where Contractor incurs additional cost or delay in the Project Schedule from its Major Subcontractors due to Owner's request to add additional Witness Points and/or Hold Points beyond those identified by Contractor, Contractor shall be entitled to a Change Order pursuant to Article 9. Contractor shall provide Owner access to or copies of these manufacturing and fabrication schedules for Equipment identified in Exhibit Q and the regular updates to these schedules, such that Owner has advance notice of approaching scheduled Witness Points and Hold Points. Owner shall be notified in writing by Contractor of Owner-designated Witness Points and Hold Points as soon as practicable but no later than [**] Business Days prior to the scheduled activity. Owner shall acknowledge the notification of Owner-designated Hold Points within [**] Business Days and indicate whether or not it intends to attend the activity that is the subject of the Hold Point.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement, Limited Agency Agreement (South Carolina Electric & Gas Co)

AutoNDA by SimpleDocs

Witness and Hold Points. (a) Following the selection of a specific vendor for Equipment identified in Exhibit Q that is part of the Standard Plant and for which there are contractual Witness Points and Hold Points, Contractor shall identify the associated Witness Points and Hold Points via inclusion of the Witness Points and Hold Points in the manufacturing and fabrication plans for the Equipment. After review, Owner may identify additional Witness Points and Hold Points and Owner shall notify Contractor of any Owner-designated Witness Points or Hold Points that they shall attend. In cases where Contractor incurs additional cost or delay in the Project Schedule from its Major Subcontractors due to Owner's request to add additional Witness Points and/or Hold Points beyond those identified by Contractor, Contractor shall be entitled to a Change Order pursuant to Article 9. Contractor shall provide Owner access to or copies of these manufacturing and fabrication schedules for Equipment identified in Exhibit Q and the regular updates to these schedules, such that Owner has advance notice of approaching scheduled Witness Points and Hold Points. Owner shall be notified in writing by Contractor of Owner-Owner- designated Witness Points and Hold Points as soon as practicable but no later than [**] ten (10) Business Days prior to the scheduled activity. Owner shall acknowledge the notification of Owner-designated Hold Points within [**] five (5) Business Days and indicate whether or not it intends to attend the activity that is the subject of the Hold Point.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement

Witness and Hold Points. (a) Following the selection of a specific vendor for Equipment identified in Exhibit Q that is part of the Standard Plant and for which there are contractual Witness Points and Hold Points, Contractor shall identify the associated Witness Points and Hold Points via inclusion of the Witness Points and Hold Points in the manufacturing and fabrication plans for the Equipment. After review, Owner may identify additional Witness Points and Hold Points and Owner shall notify Contractor of any Owner-designated Witness Points or Hold Points that they shall attend. In cases where Contractor incurs additional cost or delay in the Project Schedule from its Major Subcontractors due to Owner's request to add additional Witness Points and/or Hold Points beyond those identified by Contractor, Contractor shall be entitled to a Change Order pursuant to Article 9. Contractor shall provide Owner access to or copies of these manufacturing and fabrication schedules for Equipment identified in Exhibit Q and the regular updates to these schedules, such that Owner has advance notice of approaching scheduled Witness Points and Hold Points. Owner shall be notified in writing by Contractor of Owner-designated Witness Points and Hold Points as soon as practicable but no later than [**] ten (10) Business Days prior to the scheduled activity. Owner shall acknowledge the notification of Owner-designated Hold Points within [**] five (5) Business Days and indicate whether or not it intends to attend the activity that is the subject of the Hold Point.

Appears in 1 contract

Samples: Procurement and Construction Agreement (South Carolina Electric & Gas Co)

AutoNDA by SimpleDocs

Witness and Hold Points. (a) Following the selection of a specific vendor for Equipment identified in Exhibit Q that is part of the Standard Plant and for which there are contractual Witness Points and Hold Points, Contractor shall identify the associated Witness Points and Hold Points via inclusion of the Witness Points and Hold Points in the manufacturing and fabrication plans for the Equipment. After review, Owner may identify additional Witness Points and Hold Points and Owner shall notify Contractor of any Owner-designated Witness Points or Hold Points that they shall attend. In cases where Contractor incurs additional cost or delay in the Project Schedule from its Major Subcontractors due to Owner's ’s request to add additional Witness Points and/or Hold Points beyond those identified by Contractor, Contractor shall be entitled to a Change Order pursuant to Article 9. Contractor shall provide Owner access to or copies of these manufacturing and fabrication schedules for Equipment identified in Exhibit Q and the regular updates to these schedules, such that Owner has advance notice of approaching scheduled Witness Points and Hold Points. Owner shall be notified in writing by Contractor of Owner-designated Witness Points and Hold Points as soon as practicable but no later than [**] Business Days prior to the scheduled activity. Owner shall acknowledge the notification of Owner-designated Hold Points within [**] Business Days and indicate whether or not it intends to attend the activity that is the subject of the Hold Point.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Scana Corp)