Weather Days. The EMP proposal shall include in its assumptions and clarifications the number of "weather days" that are included as an allowance in the proposed schedule and Amendment No. 1 shall specify the agreed number of weather days. Weather impacts will only constitute Excusable Delays to the extent they exceed the allowance in Amendment No. 1 and otherwise meet the criteria for an Excusable Delay.