Weather Days. Contractor shall submit a written request to the City Project Manager (e-mail is the preferred method) for additional days for which work is suspended or delayed by weather. Contractor performance and execution of work will be considered in the determination for granting additional days. 3. Point repairs will be paid per stick 14LF of pipe. If 2β of pipe is used, a full stick will be paid for. If 16β of pipe is used, 2 sticks of pipe will be paid for. A - 1