Common use of Weather Days Clause in Contracts

Weather Days. The Contractor shall submit a written request to the City Project Manager (email is the preferred method) for additional days for which work is suspended or delayed by weather. Weather days shall be reconciled with each monthly pay application for the time period which the application is submitted and shall be final. Contractor performance and execution of work will be considered in the determination for granting additional days.

Appears in 1 contract

Samples: Agreement

AutoNDA by SimpleDocs

Weather Days. The Contractor shall submit a written request to the City Project Manager (email is the preferred method) for additional days for which work is suspended or delayed by weather. Weather days shall be reconciled with each monthly pay application for the time period which the application is submitted and shall be final. Contractor performance and execution of work will be considered in the determination for granting additional days.

Appears in 1 contract

Samples: Agreement for Annual Sidewalk Maintenance and Repair Services

Weather Days. The Contractor shall submit a written request to the City Project Manager (email is the preferred method) for additional days for which work is suspended or delayed by weather. Weather days shall be reconciled with each monthly pay application for the time period in which the application is submitted and shall be final. Contractor performance and execution of work will be considered in the determination for granting additional days.

Appears in 1 contract

Samples: www.prorfx.com

AutoNDA by SimpleDocs

Weather Days. The Contractor shall submit a written request to the City Project Manager (email is the preferred method) for additional days for which work is suspended or delayed by weather. Weather days shall be reconciled with each monthly pay application for the time period which the application is submitted and shall be final. Contractor performance and execution of work will be considered in the determination for granting additional days.. CONTRACTOR RESPONSIBILITIES Exhibit A – SCOPE OF WORK CONTRACT# GRM/220512 as acceptable to the City of destroyed or damaged property within forty-eight (48) hours of notification from the City. CONTRACTOR EMPLOYEES AND EQUIPMENT

Appears in 1 contract

Samples: Agreement for Demolition And