Common use of Weather Data Clause in Contracts

Weather Data. No weather data are included in this specifications and the contractor is referred to the Weather Bureau, Department of transport, ▇▇▇▇▇▇▇ ▇▇▇ ▇▇▇▇, ▇▇▇▇▇▇▇▇ ▇▇▇▇. The contract places the responsibility on the contractor to foresee inclement weather. The contractor shall take into account large variations in the weather patterns. No extension of time will be granted for delays arising out of normal weather conditions Where the abnormal, unfavourable weather conditions are experienced, an extension of the contract period may be considered by the Employer, as stated in the conditions of contract. No claim for additional Preliminary and General or escalation of the contract price for the extended period will be granted.

Appears in 2 contracts

Sources: Nec3 Engineering and Construction Short Contract (Ecsc3), Nec3 Engineering and Construction Short Contract (Ecsc3)