Common use of Variation to Implementation Plan Clause in Contracts

Variation to Implementation Plan. The Implementation Plan may be varied in accordance with the provisions of Clauses 4.3.1, 4.3.2 and 4.3.3 below: 4.3.1 The Implementation Plan may be varied by the written agreement of the parties. 4.3.2 If: 4.3.2.1 the Contractor is prevented or delayed from carrying out its obligations under this Contract in accordance with the Implementation Plan as a direct consequence of a failure by the Purchaser (or a third party supplier to the Purchaser) to perform a Purchaser Responsibility on or before the relevant date set out in the Implementation Plan (other than to the extent caused by a preceding breach of this Contract by the Contractor) (in this Clause 4.3 each a "Purchaser Delay Event"); and 4.3.2.2 the Contractor has promptly served a written notice on Purchaser setting out details of that Purchaser Delay Event and referring to this Clause 4.3, then: