Variation to Implementation Plan. The Implementation Plan may be varied in accordance with the provisions of Clauses 4.3.1, 4.3.2 and 4.3.3 below: 4.3.1 The Implementation Plan may be varied by the written agreement of the parties. 4.3.2 If: 4.3.2.1 the Contractor is prevented or delayed from carrying out its obligations under this Contract in accordance with the Implementation Plan as a direct consequence of a failure by the Purchaser (or a third party supplier to the Purchaser) to perform a Purchaser Responsibility on or before the relevant date set out in the Implementation Plan (other than to the extent caused by a preceding breach of this Contract by the Contractor) (in this Clause 4.3 each a "Purchaser Delay Event"); and 4.3.2.2 the Contractor has promptly served a written notice on Purchaser setting out details of that Purchaser Delay Event and referring to this Clause 4.3, then: