Transmission Delay. Either or both of the Guaranteed Project Milestones may be extended on a day for day basis for a cumulative period equal to no more than six (6) months if Seller has used commercially reasonable efforts (including compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades, if any, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date and Seller has worked diligently to resolve the delay (“Transmission Delay”);