Transmission Delay Sample Clauses
Transmission Delay. The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than six (6) months if Seller has used commercially reasonable efforts (including compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades, if any, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date, and such delay is not caused by Seller, and Seller has worked diligently to resolve the delay (“Transmission Delay”);
Transmission Delay. Either or both of the Guaranteed Project Milestones may be extended on a day for day basis for a cumulative period equal to no more than six (6) months if Seller has used commercially reasonable efforts (including compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades, if any, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date and Seller has worked diligently to resolve the delay (“Transmission Delay”);
Transmission Delay. Either or both of the Guaranteed Project Milestones may be extended on a day for day basis for a cumulative period equal to one hundred and eighty (180) days if Seller has used commercially reasonable efforts (including but not limited to compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and payment of all applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades needed, if any, in order to interconnect the Project to the CAISO Grid, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date for any reason other than a Force Majeure event or event caused by Seller, and Seller has worked diligently to resolve the delay (“Transmission Delay”);
Transmission Delay. Provided that the Mechanical Completion and Project Testing Completion, as defined in Appendix IV-2, have already occurred, the Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than six (6) months if Seller has used commercially reasonable efforts (including compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades, if any, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date, and such delay is not caused by Seller, and Seller has worked diligently to resolve the delay (“Transmission Delay”);
