Transmission Delay Sample Clauses

Transmission Delay. The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than six (6) months if Seller has used commercially reasonable efforts (including compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades, if any, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date, and such delay is not caused by Seller, and Seller has worked diligently to resolve the delay (“Transmission Delay”);
AutoNDA by SimpleDocs
Transmission Delay. Either or both of the Guaranteed Project Milestones may be extended on a day for day basis for a cumulative period equal to no more than six (6) months if Seller has used commercially reasonable efforts (including compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades, if any, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date and Seller has worked diligently to resolve the delay (“Transmission Delay”);
Transmission Delay. Provided that the Mechanical Completion and Project Testing Completion, as defined in Appendix IV-2, have already occurred, the Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than six (6) months if Seller has used commercially reasonable efforts (including compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades, if any, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date, and such delay is not caused by Seller, and Seller has worked diligently to resolve the delay (“Transmission Delay”);
Transmission Delay. Either or both of the Guaranteed Project Milestones may be extended on a day for day basis for a cumulative period equal to one hundred and eighty (180) days if Seller has used commercially reasonable efforts (including but not limited to compliance with all CAISO, PTO, FERC or other requirements, as applicable, and Seller’s timely submission of all required documents and payment of all applicable fees) to have the Project physically interconnected to the CAISO Grid and to complete all Electric System Upgrades needed, if any, in order to interconnect the Project to the CAISO Grid, but such interconnection or Electric System Upgrades cannot be completed by the Guaranteed Commercial Operation Date for any reason other than a Force Majeure event or event caused by Seller, and Seller has worked diligently to resolve the delay (“Transmission Delay”);

Related to Transmission Delay

  • No Transmission Delivery Service The execution of this Agreement does not constitute a request for, nor agreement to provide, any Transmission Service under the NYISO OATT, and does not convey any right to deliver electricity to any specific customer or Point of Delivery. If Developer wishes to obtain Transmission Service on the New York State Transmission System, then Developer must request such Transmission Service in accordance with the provisions of the NYISO OATT.

  • Transmission Delivery Service Implications Network Resource Interconnection Service allows Interconnection Customer's Large Generating Facility to be designated by any Network Customer under the Tariff on Transmission Provider's Transmission System as a Network Resource, up to the Large Generating Facility's full output, on the same basis as existing Network Resources interconnected to Transmission Provider's Transmission System, and to be studied as a Network Resource on the assumption that such a designation will occur. Although Network Resource Interconnection Service does not convey a reservation of transmission service, any Network Customer under the Tariff can utilize its network service under the Tariff to obtain delivery of energy from the interconnected Interconnection Customer's Large Generating Facility in the same manner as it accesses Network Resources. A Large Generating Facility receiving Network Resource Interconnection Service may also be used to provide Ancillary Services after technical studies and/or periodic analyses are performed with respect to the Large Generating Facility's ability to provide any applicable Ancillary Services, provided that such studies and analyses have been or would be required in connection with the provision of such Ancillary Services by any existing Network Resource. However, if an Interconnection Customer's Large Generating Facility has not been designated as a Network Resource by any load, it cannot be required to provide Ancillary Services except to the extent such requirements extend to all generating facilities that are similarly situated. The provision of Network Integration Transmission Service or firm Point-to-Point Transmission Service may require additional studies and the construction of additional upgrades. Because such studies and upgrades would be associated with a request for delivery service under the Tariff, cost responsibility for the studies and upgrades would be in accordance with FERC's policy for pricing transmission delivery services. Network Resource Interconnection Service does not necessarily provide Interconnection Customer with the capability to physically deliver the output of its Large Generating Facility to any particular load on Transmission Provider's Transmission System without incurring congestion costs. In the event of transmission constraints on Transmission Provider's Transmission System, Interconnection Customer's Large Generating Facility shall be subject to the applicable congestion management procedures in Transmission Provider's Transmission System in the same manner as Network Resources. There is no requirement either at the time of study or interconnection, or at any point in the future, that Interconnection Customer's Large Generating Facility be designated as a Network Resource by a Network Service Customer under the Tariff or that Interconnection Customer identify a specific buyer (or sink). To the extent a Network Customer does designate the Large Generating Facility as a Network Resource, it must do so pursuant to Transmission Provider's Tariff. Once an Interconnection Customer satisfies the requirements for obtaining Network Resource Interconnection Service, any future transmission service request for delivery from the Large Generating Facility within Transmission Provider's Transmission System of any amount of capacity and/or energy, up to the amount initially studied, will not require that any additional studies be performed or that any further upgrades associated with such Large Generating Facility be undertaken, regardless of whether or not such Large Generating Facility is ever designated by a Network Customer as a Network Resource and regardless of changes in ownership of the Large Generating Facility. However, the reduction or elimination of congestion or redispatch costs may require additional studies and the construction of additional upgrades. To the extent Interconnection Customer enters into an arrangement for long term transmission service for deliveries from the Large Generating Facility outside Transmission Provider's Transmission System, such request may require additional studies and upgrades in order for Transmission Provider to grant such request.

  • Transmission The Custodian and the Fund shall comply with SWIFT’s authentication procedures. The Custodian will act on FT Instructions received via SWIFT provided the instruction is authenticated by the SWIFT system. § Written Instructions. Instructions may be transmitted in an original writing that bears the manual signature of an Authorized Person(s).

  • Transmission Credits No later than thirty (30) days prior to the Commercial Operation Date, the Interconnection Customer may make a one-time election by written notice to the CAISO and the Participating TO to receive Congestion Revenue Rights as defined in and as available under the CAISO Tariff at the time of the election in accordance with the CAISO Tariff, in lieu of a refund of the cost of Network Upgrades in accordance with Article 11.4.1.

  • No Transmission Service The execution of this LGIA does not constitute a request for, nor the provision of, any transmission service under the CAISO Tariff, and does not convey any right to deliver electricity to any specific customer or point of delivery.

  • Data Transmission The procedures for transmitting load obligation data to PJM for DS Supplier’s DS Load shall be as set forth by PJM.

  • Loop Transmission Types 3.1 Subject to the conditions set forth in Section 1 of this Attachment, Verizon shall allow CBB to access Loops unbundled from local switching and local transport, in accordance with this Section 3 and the rates and charges provided in the Pricing Attachment. Verizon shall allow CBB access to Loops in accordance with, but only to extent required by, Applicable Law. The available Loop types are as set forth below:

  • Transmission Charge The cost for transporting electricity from the generation source to your electric distribution company. For most electric customers who select a new supplier, transmission costs will be included in the charges from your new supplier. The Federal Energy Regulatory Commission regulates retail transmission prices and services. This charge will vary with your source of supply.

  • Data Transmission Control Except as necessary for the provision of the Cloud Services in accordance with the Agreement, Personal Data must not be read, copied, modified or removed without authorization during transfer. Where data carriers are physically transported, adequate measures are implemented at SAP to provide the agreed-upon service levels (for example, encryption and lead-lined containers). Measures: • Personal Data in transfer over SAP internal networks is protected according to SAP Security Policy. • When data is transferred between SAP and its customers, the protection measures for the transferred Personal Data are mutually agreed upon and made part of the relevant agreement. This applies to both physical and network based data transfer. In any case, the Customer assumes responsibility for any data transfer once it is outside of SAP-controlled systems (e.g. data being transmitted outside the firewall of the SAP Data Center).

  • Interoffice Transmission Facilities BellSouth shall provide nondiscriminatory access, in accordance with FCC Rule 51.311 and Section 251(c)(3) of the Act, to interoffice transmission facilities on an unbundled basis to <<customer_name>> for the provision of a telecommunications service.

Time is Money Join Law Insider Premium to draft better contracts faster.