Transition Costs. The Transition Costs are payable by Company to Provider up to the amount shown in Attachment D.4 of Exhibit D and will be paid in installments upon achievement of Transition Milestones as set forth in the Transition Plan. Transition Milestones will be extended on a day-for-day basis for any critical path delays in achieving such Transition Milestones due to any Force Majeure Events or Excused Company-Related Delays.
Appears in 3 contracts
Sources: Integrated Facilities Management Services Agreement, Integrated Facilities Management Services Agreement (Amgen Inc), Integrated Facilities Management Services Agreement (Amgen Inc)