Time Parameters. 1.4.1 The Consultant shall begin work under this Agreement upon receipt of a written notice to proceed from the Owner. 1.4.2 Milestones for completion of the work under this Agreement as follows: 1. Preliminary design plans including type/size/location for all structures (preliminary design) and detail elements for a design public hearing and construction right-of-way needs shall be completed and accepted on or before [Insert date here] or [Insert days] calendar days after receiving the notice to proceed (whichever is greater). 2. Final design, contract plans and specifications and estimates shall be completed and in a form acceptable to the Owner on or before [Insert date here]. 3. Completion of all work under this agreement shall be on or before [Insert date here] unless extended by written approval of the Contract Administrator or adjusted by supplemental agreement. 1.4.3 The Consultant shall not begin final design activities until after the Owner has been notified by the Iowa DOT that FHWA Environmental Concurrence has been obtained. Upon receipt of such notice, the Owner will provide the Consultant notice to proceed with final design activities.
Appears in 2 contracts
Sources: Consultant Contract, Consultant Contract
Time Parameters. 1.4.1 The Consultant shall begin work under this Agreement upon receipt of a written notice to proceed from the Owner.
1.4.2 Milestones for completion of the work under this Agreement as follows:
1. Preliminary design plans including type/size/location for all structures (preliminary design) and detail elements for a design public hearing and construction right-of-way needs shall be completed and accepted on or before [Insert [Insert date here] here] or [Insert days] [Insert days] calendar days after receiving the notice to proceed (whichever is greater).
2. Final design, contract plans and specifications and estimates shall be completed and in a form acceptable to the Owner on or before [Insert [Insert date here].here].
3. Completion of all work under this agreement shall be on or before [Insert [Insert date here] here] unless extended by written approval of the Contract Administrator or adjusted by supplemental agreement.
1.4.3 The Consultant shall not begin final design activities until after the Owner has been notified by the Iowa DOT that FHWA Environmental Concurrence has been obtained. Upon receipt of such notice, the Owner will provide the Consultant notice to proceed with final design activities.