Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the Authority’s Engineer shall only determine the value of Works associated with Maintenance.
Appears in 3 contracts
Samples: Epc Agreement, Draft Contract Agreement, Procurement and Construction)
Termination Payment for Force Majeure Event. 21.8.1 19.8.1 In the event of this Agreement being terminated on account of a Non-Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the Authority’s Engineer shall only determine the value of Works associated with Maintenance21.5.
Appears in 3 contracts
Samples: Model Agreement, Model Agreement, And Construction Agreement
Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Non- Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the Authority’s Engineer shall only determine the value of Works associated with Maintenance.
Appears in 2 contracts
Samples: Draft Contract Agreement, And Construction Agreement
Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the Authority’s Authority‟s Engineer shall only determine the value of Works associated with Maintenance.
Appears in 2 contracts
Samples: (Engineering Procurement and Construction, Procurement and Construction Agreement
Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Non- Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the Authority’s Authority‟s Engineer shall only determine the value of Works associated with Maintenance.
Appears in 1 contract
Samples: Draft Contract Agreement
Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Non- Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the Authority’s Engineer shall only determine the value of Works associated with Maintenance.
Appears in 1 contract
Samples: Agreement
Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the AuthorityEmployer’s Engineer shall only determine the value of Works associated with Maintenance.
Appears in 1 contract
Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Maintenance Period, the Authority’s AUTHORITY’S/GMDAs Engineer shall only determine the value of Works associated with Maintenance.
Appears in 1 contract
Samples: Engineering Procurement And
Termination Payment for Force Majeure Event. 21.8.1 In the event of this Agreement being terminated on account of a Non-Political Event, the Termination Payment shall be an amount equal to the sum payable under Clause 23.5. Provided that in the event Termination occurs during the Operation and Maintenance Period, the AuthorityEmployer’s Engineer shall only determine the value of Works associated with Operation and Maintenance.
Appears in 1 contract
Samples: And Construction Agreement