Task 2 Electrical Generation. a. Perform repair and recommissioning of existing stationary PREPA power plants. At completion of this task, perform functional tests/recommissioning on all elements to ensure operability. Functional test results shall be documented and submitted for government/PREPA review. b. Provide all temporary power connections and temporary portable generators for standby power capability during all phases of work. c. Provide temporary generators and connections to power substations, critical buildings, and other facilities as requested. d. Operate and maintain generators as requested. e. Perform recovery and rehabilitation of FEMA owned generators, either in the field or at the Logistics center/remote storage site.