Supporting Documentation. The Contractor shall submit all claims in the following format: (1) Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made (2) List of documents relating to claim: (A) Specifications (B) Drawings (C) Clarifications (Requests for Information) (D) Schedules (E) Other (3) Chronology of events and correspondence (4) Analysis of claim merit (5) Analysis of claim cost (6) Time impact analysis in CPM format
Appears in 22 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Supporting Documentation. The Contractor shall submit all claims in the following format:
(1) 3.10.3.1 Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made
(2) 3.10.3.2 List of documents relating to claim:
(A) Specifications
(B) Drawings
(C) Clarifications (Requests for Information)
) (D) Schedules (E) Other
(3) Other 3.10.3.3 Chronology of events and correspondence
(4) Analysis of claim merit
(5) Analysis of claim cost
(6) Time impact analysis in CPM format
Appears in 11 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Supporting Documentation. The Contractor shall submit all claims in the following format:
(1) 9.4.1 Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made
(2) 9.4.2 List of documents relating to claim:
(A) Specifications
(B) Drawings
(C) Clarifications (Requests for Information)
(D) Schedules (E) Other
(3) Other 9.4.3 Chronology of events and correspondence
(4) 9.4.4 Analysis of claim merit
(5) 9.4.5 Analysis of claim cost, including calculations and supporting documents
(6) 9.4.6 Time impact analysis in CPM format
Appears in 2 contracts
Sources: Contract for Wood Replacement Services, Contract for Painting Services
Supporting Documentation. The Contractor shall submit all claims in the following format:
(1) Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made.
(2) List of documents relating to claim:
(Aa) Specifications;
(Bb) Drawings;
(Cc) Clarifications (Requests for Request For Information);
(Dd) Schedules Schedules;
(Ee) Other.
(3) Chronology of events and correspondence.
(4) Analysis of claim merit.
(5) Analysis of claim cost.
(6) Time impact analysis in CPM format.
Appears in 2 contracts
Sources: Construction Services Agreement, Construction Services Agreement
Supporting Documentation. The Contractor shall submit all claims Claims in the following format:
(1) 3.10.3.1 Summary of claim Claim merit and price, reference Contract Document provisions pursuant to which the claim Claim is made
(2) 3.10.3.2 List of documents relating to claimClaim:
(A) Specifications
(B) Drawings
(C) Clarifications (Requests for Information)
) (D) Schedules (E) Other
(3) Other 3.10.3.3 Chronology of events and correspondence
(4) Analysis of claim merit
(5) Analysis of claim cost
(6) Time impact analysis in CPM format