Subcontract Bidding Process Sample Clauses
Subcontract Bidding Process. 4.5.1 The CM shall create a Bid package for each Subcontract and solicit Bids from qualified prospective Bidders identified under Section 4.4 for that Bid package in accordance with the Project Schedule.
4.5.1.1 Notwithstanding the Project Schedule, the CM shall not solicit Bids for any Bid package for any Work that is not the subject of an executed GMP Amendment unless the Contracting Authority first agrees otherwise in writing.
4.5.1.2 The CM shall not solicit a Bid from any Bidder not prequalified under Section 4.4 unless the Contracting Authority first agrees otherwise in writing.
Subcontract Bidding Process. 7.2.1 During the Subcontract Bidding Process, the Contractor shall, as appropriate, forward questions from Bidders to the A/E. The A/E shall promptly respond to those questions.
7.2.2 During the Subcontract Bidding Process, the A/E shall prepare addenda for issuance to the prospective Bidders through the Contractor.
7.2.3 No less than 10 days beforeBefore Work is to be performed by any Subcontractor, or within a shorter period as mutually agreed by the Contractor and Contracting Authority, the Contractor shall submit to the A/E a Subcontractor and Material Supplier Declaration form through which the Contractor identifies the Subcontractor. After receiving the form, the A/E shall verify that it is complete and deliver it to the Contracting Authority and Owner. If the A/E finds the form incomplete, the A/E shall return it to the Contractor and identify the incomplete information.
7.2.3.1 If the Project is administered using the State’s web-based project management software, the A/E shall review and recommend approval or disapproval to the Contracting Authority of each Subcontractor through the “Subcontractor Supplier Declaration” business process.
Subcontract Bidding Process. 4.5.1 The DB shall create a Bid package for each Subcontract and solicit Bids from qualified prospective Bidders identified under Section 4.4 for that Bid package in accordance with the Project Schedule. Execution of a GMP Amendment concerning the Work for which the DB is soliciting Bids is not a condition precedent to commencement or completion of the Subcontract Bidding Process.
4.5.2 At completion of the Subcontract Bidding Process for each Subcontract and no later than 15 days before the Work is scheduled to begin under that Subcontract, the DB and Contracting Authority will meet to review Bids of qualified prospective Bidders identified under Section 4.4 for that Subcontract and determine to which prospective Bidder the DB will award the Subcontract. During the review meeting, the DB shall identify the prospective Bidder to whom the DB proposes to award the Subcontract.
4.5.2.1 Each Bidder to whom the DB proposes to award a Subcontract shall to the DB’s reasonable satisfaction
(1) be qualified to perform the subcontracted portion of the Work and (2) have submitted a Bid that conforms to the requirements of the Contract Documents.
.1 For the purpose of evaluating and reconciling the Bids, the DB may conduct scope-review meetings with Bidders that are usual and customary within the Bidders’ trade. Bids that have been reconciled with other Bids for the same scope of Work through that review process will be considered in conformance with the Contract Documents.
.2 The DB is not required to propose to award the Subcontract to the Bidder that submitted the lowest Bid.
4.5.2.2 If the Contracting Authority does not reject the DB-proposed Bidder, the DB shall enter into the Subcontract with the selected Bidder.
.1 All Subcontracts shall be on the State of Ohio Subcontract Form prescribed by OAC Section 153:1-03- 02. .2 No less than 10 days before Work is to be performed by the Subcontractor, or within a shorter period as mutually agreed by the DB and Contracting Authority, the DB shall submit to the Contracting Authority a Subcontractor and Material Supplier Declaration form through which the DB identifies the Subcontractor. After receiving the form and Subcontract, the Contracting Authority shall verify that they are complete and deliver them to the Owner. If the Contracting Authority finds the form and Subcontract are incomplete, the Contracting Authority shall return them to the DB and identify the incomplete information.
Subcontract Bidding Process. 7.2.1 During the Subcontract Bidding Process, the Contractor shall, as appropriate, forward questions from Bidders to the A/E. The A/E shall promptly respond to those questions.
7.2.2 During the Subcontract Bidding Process, the A/E shall prepare addenda for issuance to the prospective Bidders through the Contractor.
7.2.3 Before Work is to be performed by any Subcontractor, the Contractor shall submit to the A/E a Subcontractor and Material Supplier Declaration form through which the Contractor identifies the Subcontractor. After receiving the form, the A/E shall verify that it is complete and deliver it to the Contracting Authority and Owner. If the A/E finds the form incomplete, the A/E shall return it to the Contractor and identify the incomplete information.
7.2.3.1 If the Project is administered using the State’s web-based project management software, the A/E shall review and recommend approval or disapproval to the Contracting Authority of each Subcontractor through the “Subcontractor Supplier Declaration” business process.
Subcontract Bidding Process. Design Builder represents that it has complied with the bidding requirements set forth in Public Contract Code sections 22166 (a) and will comply with the bidding requirements of Public Contract Code section 4100, et seq., for procuring any subcontracts where Subcontractors are not listed by Design Builder in exhibit 5B. In addition, the Design Builder will: (i) develop bidders’ interest in the Project and endeavor to have at least 3 bids for all trades; (ii) establish bidding schedules in accordance with the procurement requirements set forth in the Project Schedule (Exhibit 5A); (iii) develop Subcontractor scopes of work, and package and issue bidding documents to pre-qualified, interested bidders; (iv) evaluate bidder prequalification and bids to determine the best subcontractor suited for the Project in accordance with Public Contract Code section 22166 (b) (3); and (v) enter written subcontract with the most responsive, responsible bidder based on the bid criteria and pursuant to this Sections 6.7 and 6.8. Design Builder may not knowingly subcontract with a Subcontractor or supplier that prepared portions of the Project Documents (Exhibit 3A).
