Software – Acceptance Testing. 2.1 The Customer shall carry out each set of the Acceptance Tests in accordance with the Project Plan. 2.2 If the Software does not pass any of the Acceptance Tests, the Customer may, by notice to the Supplier, either: (a) require the Supplier, at no cost to the Customer, to rework the Software to pass repeat Acceptance Tests within [20] Business Days of the previous Acceptance Test failure (or such other period as the parties may agree in writing) and the provisions of this paragraph 2 shall apply to the repeat Acceptance Tests; or (b) consider the Software to have passed the relevant Acceptance Tests and allow the Software to progress to the next stage.