Snagging Items. In the event that a Certificate of Availability for a Phase is expected to be subject to Snagging Items: 20.7.1 the Independent Certifier shall within five (5) Business Days of the issue of the relevant Certificate of Availability issue to the Contractor and the Authority a list of the relevant snagging items for that Phase (the Snagging List). Within five (5) Business Days of receipt from the Independent Certifier of the Snagging List the Contractor shall provide to the Authority and the Independent Certifier a reasonable programme for making good each Snagging Item set out in the Snagging List provided that such programme shall require that each Snagging Item shall be made good within one twenty (20) Business Days of the date of the agreement or determination of that programme or within such time as is reasonably practicable. The parties shall seek to agree such programme and in default of agreement shall refer the matter for determination under the Dispute Resolution Procedure. The programme agreed or determined in accordance with this clause 20.7.1 (Snagging Items) shall be known as the Snagging Programme; and 20.7.2 the Contractor shall procure that each Snagging Item is made good in accordance with the Snagging Programme to the satisfaction of the Independent Certifier. If any Snagging Item has not been rectified by the date set out in the Snagging Programme then the Authority shall be entitled to effect such repairs as may be necessary and recover the costs of doing so from the Contractor.
Appears in 2 contracts
Sources: Project Agreement, Project Agreement
Snagging Items. In the event that a Test Certificate of Availability for a Phase Facility is expected expressed to be subject to Snagging Items:
20.7.1 21.5.1 the Independent Certifier shall within five (5) Business Days of shall, at the issue of same time as it issues the relevant Certificate of Availability Test Certificate, issue to the Contractor and the Authority a list of the relevant snagging items Snagging Items for that Phase the Facility (the “Snagging List”). Within five (5) Business Days of receipt from the Independent Certifier of the Snagging List the Contractor shall provide to the Authority and the Independent Certifier a reasonable programme for making good each Snagging Item set out in the Snagging List provided that such programme shall require that each Snagging Item shall be made good within one twenty (20) Business Days of the date of the agreement or determination provision of that programme or within such time as is reasonably practicable. The parties Parties shall seek to agree such programme and in default of agreement shall refer the matter for determination under the Clause 60 (Dispute Resolution ProcedureResolution). The programme agreed or determined in accordance with this clause 20.7.1 Clause 21.5 (Snagging Items) shall be known as the Snagging Programme; and
20.7.2 21.5.2 the Contractor shall procure that each Snagging Item is made good rectified in accordance with the Snagging Programme and to the satisfaction of the Independent Certifier. If any Snagging Item has not been rectified by the date set out in the Snagging Programme then the Authority shall be entitled to effect such repairs as may be necessary and recover the costs of doing so from the ContractorContractor as a debt.
Appears in 2 contracts
Sources: Residual Waste Treatment Contract, Residual Waste Treatment Contract
Snagging Items. In the event that a Certificate of Availability for a Phase Dwelling or a Property is expected to be subject to Snagging Items:
20.7.1 20.4.1 the Independent Certifier shall within five (5) Business Working Days of the issue of the relevant Certificate of Availability issue to the Contractor and the Authority City Council a list of the relevant snagging items Snagging Items for that Phase Dwelling or Property (the "Snagging List"). Within five (5) Business Working Days of receipt from the Independent Certifier of the Snagging List the Contractor shall provide to the Authority City Council and the Independent Certifier a reasonable programme for making good each Snagging Item set out in the Snagging List provided that such programme shall require that each Snagging Item shall be made good within one twenty (20) Business Working Days of the date of the agreement or determination of that programme or within such time as is reasonably practicable. The parties shall seek to agree such programme and in default of agreement shall refer the matter for determination under the Dispute Resolution Procedure. The programme agreed or determined in accordance with this clause 20.7.1 20.4 (Snagging Items) shall be known as the "Snagging Programme"; and
20.7.2 20.4.2 the Contractor shall procure that each Snagging Item is made good in accordance with the Snagging Programme to the satisfaction of the Independent Certifier. If any Snagging Item has not been rectified by the date set out in the Snagging Programme then the Authority City Council shall be entitled to effect such repairs as may be necessary and recover the costs of doing so from the Contractor.
Appears in 1 contract
Sources: Project Agreement