Common use of Settlement Proposal Clause in Contracts

Settlement Proposal. After termination under this Article 8, or for any other category of termination for which the Contract Documents expressly permit Design-Builder to recover under this Article 8, Design-Builder shall submit a final termination settlement proposal to Department in the form and with the certification prescribed by Department. Design-Builder shall submit the proposal promptly, but no later than ninety (90) days from the effective date of termination unless Design-Builder has requested a time extension in writing within such ninety (90)-day period and Department has agreed in writing to allow such an extension.

Appears in 4 contracts

Samples: Comprehensive Agreement, Comprehensive Agreement, Comprehensive Agreement