Scheduled Outages. (a) The Company shall submit its desired schedule of Scheduled Outage periods (including the duration of each such period) to BPDB six (6) Months before the Required Commercial Operations Date of the Facility and on the date falling every six (6) Months after the Commercial Operations Date for each subsequent twelve (12)
Appears in 8 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Scheduled Outages. (a) The Company shall submit its desired schedule of Scheduled Outage periods (including the duration of each such period) to BPDB six fifteen (615) Months before the Required Commercial Operations Date of the Facility and on the date falling every six (6) Months after the Commercial Operations Date for each subsequent twelve (12)
Appears in 1 contract
Samples: Power Purchase Agreement