Common use of Schedule Update Clause in Contracts

Schedule Update. As and when requested by the DGS Project Manager but no less often than monthly, the Project Management Contractor shall review the builder’s then current schedule for adequacy and completeness. The Project Management Contractor shall inform the DGS Project Manager of any significant deficiencies in the builder’s then current schedule. As part of such reviews, the Project Management Contractor shall evaluate whether the schedule complies with the requirements of the underlying contract and contains durations and logic ties that are reasonable and appropriate. Among other things, the Project Management Contractor shall identify any activity that has a planned duration of more than two (2) months.

Appears in 2 contracts

Sources: Project Management Services Agreement, Project Management Services Agreement