Schedule Format. The Construction Schedule shall be planned and recorded with a Critical Path Method (“CPM”) schedule in the form of an activity-on-node diagram. All activity-on-node diagrams shall include the Activity Identification, Activity Description, and the type of relationship between activities, including any lead or lag time. No activity shall have duration greater than fifteen (15) business days The Construction Schedule shall depict all activities necessary for, or incidental to, performance of the Work, showing the logic (sequence, dependency), duration, and “float” of each activity, with the critical path highlighted and shall include (a) the required Commencement Date, the required dates of Architect’s Substantial Completion and Final Completion;