RFI Log. Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log with progress meeting minutes. Include the following: .1 Project name. .2 Name and address of Contractor. .3 Name and address of Contract Administrator.
Appears in 1 contract
Sources: Construction Contract
RFI Log. Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log with at each progress meeting minutesmeeting. Include the following: .1 :
1. Project name.
2. .2 State Contract Number
3. Name and address of Contractor.
4. .3 Name and address of Contract AdministratorEngineer.
5. RFI number including RFIs that were dropped and not submitted.
6. RFI description.
7. Date the RFI was submitted.
8. Date Engineer's response was received.