Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 14 contracts
Samples: Agreement, Local Authority Software Applications Call Off Terms, Local Authority Software Applications Call Off Terms
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 13 contracts
Samples: assets.crowncommercial.gov.uk, www.contractsfinder.service.gov.uk, assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (g) (Delay Payments) shall apply.
Appears in 3 contracts
Samples: assets.crowncommercial.gov.uk, assets.crowncommercial.gov.uk, assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier Service Provider becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 3 contracts
Samples: assets.crowncommercial.gov.uk, assets.crowncommercial.gov.uk, assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractContract : it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 3 contracts
Samples: assets.crowncommercial.gov.uk, assets.crowncommercial.gov.uk, assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (c) (Delay Payments) shall apply.
Appears in 2 contracts
Samples: assets.crowncommercial.gov.uk, assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer Contracting Authority as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the CustomerContracting Authority’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 2 contracts
Samples: Framework Agreement, www.hcpc-uk.org
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractContract : it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 1 contract
Samples: www.contractsfinder.service.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 1 contract
Samples: assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 7.4 (Delay Payments) shall apply.
Appears in 1 contract
Samples: assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Call-Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (g) (Delay Payments) shall apply.
Appears in 1 contract
Samples: assets.crowncommercial.gov.uk
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractLease Agreement: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (c) (Delay Payments) shall apply.
Appears in 1 contract
Samples: Lease Agreement
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractContract : it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (c) (Delay Payments) shall apply.
Appears in 1 contract
Samples: assets.crowncommercial.gov.uk