REACTIVE POWER SUPPORT Sample Clauses

REACTIVE POWER SUPPORT. Producer agrees to provide reactive capability to regulate and maintain system voltage at the Delivery Points in conformance with Bulletin No. 756, the Retail Tariff or any applicable NYISO tariff or agreement at no cost to Niagara Mohawk. Producer may seek compensation for reactive power pursuant to the terms of any applicable NYISO tariff or agreement or in any market for reactive power.
AutoNDA by SimpleDocs
REACTIVE POWER SUPPORT. Seller shall provide to Buyer, upon Buyer's request, up to 40,000 MVAR - hours of reactive power support during each Gas Supply Year during the term of this Agreement. Buyer understands that, while the Plant's VAR capability varies with ambient temperature, in no event shall Seller be able to provide reactive power support from each of Seller's three (3) generators in excess of a power factor of 0.85 in the lag (namely, providing reactive power support to Buyer's system) and unity in the lead; provided, however, that in no case shall Seller be required to provide to Buyer MVAR in excess of the maximum level the Plant can generate without reducing The Plant's ability to generate 240 MW net output as measured at the delivery point, as said maximum level is designated in the D-curve provided by Seller hereunder. As part of the monthly statement provided by Buyer to Seller pursuant to Article IV of this Agreement, Buyer shall provide a written report of the amount of reactive power support provided by Seller during the prior month. Seller shall provide to Buyer, no later than thirty (30) days prior to the Date of Commercial Operation, the D-curve for each of the Plant's generators, which D-curves shall be updated by Seller and provided to Buyer on or before each January 1 during the term of this Agreement. Seller shall provide said reactive power support (a) upon Buyer's telephonic request to the Plant control room, followed by a confirming facsimile notice, the form of which facsimile notice shall be finalized by Seller and Buyer within ten (10) days following the execution by Seller and Buyer of Amendment No. 2 to this Agreement, and (b) without compensation from Buyer. Buyer's requests for reactive power support shall specify the magnitude of the VAR support to be provided by Seller. Unless Seller determines that, for Plant security reasons, the Plant must operate at some other power factor, Seller shall operate the Plant at the power factor capability requested by Buyer until otherwise notified by Buyer.
REACTIVE POWER SUPPORT. Reactive Power will not be supplied outside of the protective limits of each Project generators.
REACTIVE POWER SUPPORT. 5.3.1. PRODUCER is required to provide reactive capability to regulate and maintain system voltage at the DELIVERY POINT in conformance with ELECTRIC SYSTEM BULLETIN No. 756. NIAGARA MOHAWK or NYPP or its successor shall establish a scheduled range of voltages or reactive power deliveries to be maintained by the generator.
REACTIVE POWER SUPPORT 

Related to REACTIVE POWER SUPPORT

  • Reactive Power 1.8.1 The Interconnection Customer shall design its Small Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range established by the Connecting Transmission Owner on a comparable basis, until NYISO has established different requirements that apply to all similarly situated generators in the New York Control Area on a comparable basis.

  • Reactive Power and Primary Frequency Response 9.6.1 Power Factor Design Criteria

  • Power Factor Design Criteria (Reactive Power A wind generating plant shall operate within a power factor within the range of 0.95 leading to 0.95 lagging, measured at the Point of Interconnection as defined in this LGIA in order to maintain a specified voltage schedule, if the Interconnection System Impact Study shows that such a requirement is necessary to ensure safety or reliability. The power factor range standard can be met by using, for example, power electronics designed to supply this level of reactive capability (taking into account any limitations due to voltage level, real power output, etc.) or fixed and switched capacitors, or a combination of the two, if agreed to by the Participating TO and CAISO. The Interconnection Customer shall not disable power factor equipment while the wind plant is in operation. Wind plants shall also be able to provide sufficient dynamic voltage support in lieu of the power system stabilizer and automatic voltage regulation at the generator excitation system if the Interconnection System Impact Study shows this to be required for system safety or reliability.

  • Power Supply Electric Power supply for carrying out his work shall be arranged by contractor on his own cost at the site and energy charges shall be borne by the contractor.

  • Payment for Reactive Power NYISO shall pay Developer for reactive power or voltage support service that Developer provides from the Large Generating Facility in accordance with the provisions of Rate Schedule 2 of the NYISO Services Tariff.

  • Capacity Interconnection Rights Pursuant to and subject to the applicable terms of the Tariff, the Interconnection Customer shall have Capacity Interconnection Rights at the Point(s) of Interconnection specified in this Interconnection Service Agreement in the amount of 550 MW.

  • Interconnection Customer Authority Consistent with Good Utility Practice, this LGIA, and the CAISO Tariff, the Interconnection Customer may take actions or inactions with regard to the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities during an Emergency Condition in order to (i) preserve public health and safety, (ii) preserve the reliability of the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities,

  • Water Supply The system may or may not meet state and local requirements. It is the right and responsibility of Buyer to determine the compliance of the system with state and local requirements. [For additional information on this subject, request the “Water Supply and Waste Disposal Notification” form.]

  • Police Powers The Grantee agrees to comply with the terms of any lawfully adopted generally applicable local ordinance necessary to the safety, health, and welfare of the public, to the extent that the provisions of the ordinance do not have the effect of limiting the benefits or expanding the obligations of the Grantee that are granted by this Franchise. This Franchise is a contract and except as to those changes which are the result of the Grantor’s lawful exercise of its general police power, the Grantor may not take any unilateral action which materially changes the mutual promises in this contract.

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades