Protective Relaying. All SPPCo. required protective relay equipment will be located within the Steamboat substation meter house. The following relays are required by SPPCo. to isolate faults between the Steamboat substation and Far West's facilities as well as to prevent Far West from islanding with a portion of SPPCo.'s system under abnormal system conditions: a. Over/under frequency b. Over/under voltage c. Synchronism check d. Overcurrent (phase and ground, possible directional) This list is not exhaustive and may be expanded and refined. SPPCo's relaying and protection design personnel will make a final determination concerning the required hardware and equipment settings.
Appears in 2 contracts
Sources: Special Facilities Agreement (Ormat Funding Corp.), Special Facilities Agreement (Brady Power Partners)