Project Taking-over Sample Clauses
POPULAR SAMPLE Copied 1 times
Project Taking-over. After the project construction is completed, the Contractor shall propose the Employer in writing to organize the project completion acceptance. The Employer shall complete the preliminary acceptance within 10 days and complete the project completion acceptance within 30 days. If the Employer fails to organize acceptance 45 days after the written application for completion acceptance of the Contractor, it shall be deemed that the project has passed the acceptance. The Contractor shall ensure 3 months normal operation after the project passes the preliminary acceptance of the Employer; if the system operates normally and passes completion acceptance, the Contractor shall handle relevant project take-over procedures (the labor costs, electric charge, pharmaceutical fee and costs of consumables etc. during the guaranteed operation shall be borne by the Employer.).
Project Taking-over. 9.1.1 Taking over by single project and/or by project. According to the specific conditions and characteristics of the project, it shall be agreed to receive by single project and/or by project in the special terms and conditions.
(1) In accordance with the provisions about post-completion test in Article 10, if the Contractor is responsible for guiding the Employer to carry out the single project and/or post-completion test, and for the assessment of the trial run, the special terms and conditions shall stipulate the sequence and time arrangement of taking over the single project or the time arrangement of taking over the project. If the Employer is responsible for the single project and/or post-completion test, and for the assessment of the trial run, the special terms and conditions shall stipulate the date of taking over the project or the sequence and time arrangement of taking over the single project.
(2) For single projects and/or projects without completion test or post-completion test, if the Contractor completes the outstanding work and defect repair, which meets the acceptance standards agreed in the contract, the project taking-over and completion acceptance shall be handled in accordance with the contract.
9.1.2 Information submitted by the Contractor when taking over the project. Except for the materials that have been submitted as agreed in Items (1) - (3) of Article 8.1.1, the categories, contents, copies and submission time of the acceptance materials for the completion test to be submitted shall be stipulated in the special terms and conditions.
Project Taking-over. 9.1.1 Taking-over by single project or (and) by project Choose one of the two options as agreement on project taking-over between the two parties. ☐ If the Contractor is responsible for guiding the Employer to conduct the test after completion for single project or (and) the project and assumes the liability for the assessment of trial operation, the sequence and time arrangement for taking over single project or the time arrangement for taking the project are listed as follows: ______________________; þ If the Employer is responsible for the test after completion for single project or (and) the project and assumes the liability for the assessment of trial operation, the sequence and time arrangement for taking over single project or the time arrangement for taking over the project are listed as follows: From the date on which the project passes the Employer’s preliminary acceptance, the Contractor shall guarantee normal operation for 3 months. If the system runs well and passes the after-completion acceptance, the hand-over of relevant project shall be conducted.