Project Completion. a. When all of the work to be performed under this Contract has been fully completed, the Contractor shall notify the Project Manager and District, in writing, setting a date for inspection. The Contractor and Subcontractor representatives shall attend the inspection. As a result of this inspection, the Project Manager will prepare a list of items ("punch list") that are incomplete or not installed according to the Contract Documents. Failure to include items on this list does not relieve the Contractor from fulfilling all requirements of the Contract Documents.
Appears in 17 contracts
Project Completion. a. When all of the construction work to be performed under this Contract has been fully completed, the Contractor shall notify the Project Manager Architect and District, in writing, setting a date for inspection. The Contractor and Subcontractor representatives shall attend the inspection. As a result of this inspection, the Project Manager Architect will prepare a list of items ("punch list") that are incomplete or not installed according to the Contract Documents. Failure to include items on this list does not relieve the Contractor from fulfilling all requirements of the Contract Documents.
Appears in 4 contracts
Samples: Lease Leaseback Agreement, Lease Leaseback Agreement, Lease Leaseback Agreement
Project Completion. a. 79.1 When all of the work to be performed under this Contract has been fully completed, the Contractor shall notify the Project Manager Architect and District, in writing, setting a date for inspection. The Contractor and Subcontractor representatives shall attend the inspection. As a result of this inspection, the Project Manager Architect will prepare a list of items ("βpunch list"β) that are incomplete or not installed according to the Contract Documents. Failure to include items on this list does not relieve the Contractor from fulfilling all requirements of the Contract Documents.
Appears in 3 contracts
Samples: Lease Leaseback Agreement, Lease Leaseback Agreement, Lease Leaseback Agreement
Project Completion. a. When all of the work to be performed under this Contract has been fully completed, the Contractor shall notify the Project Manager and DistrictMVCS, in writing, setting a date for inspection. The Contractor and Subcontractor representatives shall attend the inspection. As a result of this inspection, the Project Manager will prepare a list of items ("punch list") that are incomplete or not installed according to the Contract Documents. Failure to include items on this list does not relieve the Contractor from fulfilling all requirements of the Contract Documents.
Appears in 1 contract
Samples: Contract