PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:
Appears in 1 contract
Sources: Construction Contract
PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, Resident Engineer or Project Manager, shall submit to the Engineer, Resident Engineer or Project Manager a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, Resident Engineer or Project Manager, and monthly cash flow requirements, showing:
Appears in 1 contract
Sources: Furnish and Install Agreement
PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to WorkWork or issuance of a Work Order, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:
Appears in 1 contract
Sources: On Call Cable Infrastructure Installation Services Agreement