Progress Reports and Information Sample Clauses
The "Progress Reports and Information" clause requires one party, typically a contractor or service provider, to regularly update the other party on the status of work or project milestones. This may involve submitting written progress reports, providing data on completed tasks, or responding to specific information requests within agreed timeframes. By ensuring ongoing communication and transparency, this clause helps the receiving party monitor performance, address issues promptly, and maintain oversight throughout the duration of the project.
Progress Reports and Information. When required, the Contractor shall submit to the Owner such schedule of quantities and costs, payrolls, bills, vouchers, correct copies of all subcontracts, statements, reports, correct copies of all agreements, correspondence, and written transactions with the surety on the performance bond that have any relevance to the Work, estimates, records, and other data as the Owner may request that concerns the Work performed or to be performed under this Contract. When requested by the Owner, the Contractor shall give the Owner access to its records relating to the foregoing. (See also Article 1.2.3, Audits.) The above reports shall include, but are not limited to,
(a) written notice of dates by which specified Work will have been completed, (b) written notice of dates by which Non- Compliant Work will be made good, (c) written notice that Non-Compliant Work has been made good, (d) written notice as to the date or dates by which Work that has not been performed with equal steps and at the same rate required by the Overall Project Schedule shall have been brought into conformity with the Overall Project Schedule, (e) date by which any undisputed claim of a Subcontractor supplier, or laborer shall have been paid, (f) written advice regarding the nature and amount of any disputed claim of a Subcontractor, supplier, or laborer, and (g) information regarding Work performed under Change Orders.
Progress Reports and Information. When required, the CM/GC shall submit to the Design Professional and Owner such schedule of quantities and costs, payrolls, bills, vouchers, correct copies of all subcontracts, statements, reports, correct copies of all agreements, correspondence, and written transactions with the surety on the performance bond that have any relevance to the Work, estimates, records, and other data as the Owner may request that concerns the Work performed or to be performed under this Contract. When requested by the Owner, the CM/GC shall give the Owner access to its records relating to the foregoing. (See also Article 4.1.2, Audits.) The above reports shall include, but are not limited to, (a) written notice of dates by which specified Work will have been completed, (b) written notice of dates by which Non-Compliant Work will be made good, (c) written notice that Non-Compliant Work has been made good, (d) written notice as to the date or dates by which Work that has not been performed with equal steps and at the same rate required by the Overall Project Schedule shall have been brought into conformity with the Overall Project Schedule, (e) date by which any undisputed claim of a Subcontractor supplier, or laborer shall have been paid, (f) written advice regarding the nature and amount of any disputed claim of a Subcontractor, supplier, or laborer, and (g) information regarding Work performed under Change Orders. CM/GC Design Coordination Activities. Local Conditions. The CM/GC shall visit the site(s), become familiar with the local conditions, and correlate observable conditions with the requirements of the Contract Documents.
Progress Reports and Information. When required, the CMR shall submit to the Design Professional and Board such schedule of quantities and costs, payrolls, bills, vouchers, correct copies of all subcontracts, statements, reports, correct copies of all agreements, correspondence, and written transactions with the surety on the performance bond that have any relevance to the Work, estimates, records, and other data as the Board may request that concerns the Work performed or to be performed under this Contract. When requested by the Board, the CMR shall give the Board access to its records relating to the foregoing. (See also Section 4.1.2, Audits.) The above reports shall include, but are not limited to, (a) written notice of dates by which specified Work will have been completed, (b) written notice of dates by which Non-Compliant Work will be made good, (c) written notice that Non-Compliant Work has been made good,
Progress Reports and Information. When required, the Contractor shall submit to ATL such schedule of quantities and costs, payrolls, bills, vouchers, correct copies of all subcontracts, statements, reports, correct copies of all agreements, correspondence, and written transactions with the surety on the performance bond that have any relevance to the Work, estimates, records, and other data as ATL may request that concerns the Work performed or to be performed under this Contract. When requested by ATL, the Contractor shall give ATL prompt access to its records relating to the foregoing. To the extent applicable, the above reports shall include (a) written notice of dates by which specified Work will have been completed, (b) written notice of dates by which nonconforming Work will be made good, (c) written notice that nonconforming Work has been made good, (d) written notice as to the date or dates by which Work that has not been performed as required by the Schedule shall have been brought into conformity with the Schedule, (e) date by which any undisputed claim of Contractor Parties shall have been paid, (f) written advice regarding the nature and amount of any disputed claim of Contractor Parties, and (g) information regarding Work performed under Change Orders.
Progress Reports and Information. The Developer shall provide any information reasonably requested by the County in connection with the Development.
(a) Until such time as the Developer is entitled to issuance of a Certificate of Completion for the Development, the Developer shall provide the County with quarterly progress reports, or as reasonably requested by the County, regarding the status of the construction of the Development.
Progress Reports and Information. When required, the Contractor shall submit to the Owner such schedule of quantities and costs, payrolls, bills, vouchers, correct copies of all subcontracts, statements, reports, correct copies of all agreements, correspondence, and written transactions with the surety on the performance bond that have any relevance to the Work, estimates, records, and other data as the Owner may request that concerns the Work performed or to be performed under this Contract. When requested by the Owner, the Contractor shall give