PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager a Pre- Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase (Program) 05% $ . Schematic Design Stage 10% $ . Design Development Stage 20% $ . GMP Development Stage 20% $ . Construction Document Stage 40% $ . Buyout Stage 05% $ . 24.2.2 Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager shall allocate the Pre- Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless Owner and Construction Manager agree otherwise.
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager a Pre- Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase (Program) 05% $ . Schematic Design Stage 1005% $ . Design Development Stage 2015% $ . GMP Development Stage 2025% $ . Construction Document Stage 40% $ . Buyout Stage 0510% $ .
24.2.2 Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, the Construction Manager shall allocate the Pre- Pre-Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless the Owner and Construction Manager agree otherwise.
Appears in 1 contract
Sources: Construction Manager Agreement
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager a Pre- Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase (Program) 05% $ . $355,000.00 Schematic Design Stage 10% $ . $710,000.00 Design Development Stage 20% $ . $1,420,000.00 GMP Development Stage 20% $ . $1,420,000.00 Construction Document Stage 40% $ . $2,840,000.00 Buyout Stage 05% $ .$355,000.00
24.2.2 Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager shall allocate the Pre- Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless Owner and Construction Manager agree otherwise.
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager Design/Build Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase Stage (Program5%) 05% $ . Schematic Design Stage (10% $ . %) Design Development Stage (20% %) $ . $ $ GMP Development Stage (20% %) $ . Construction Document Documents Stage (40% %) $ . Buyout Stage 05% (5%) $ Total $
24.2.2 The Pre-Construction Phase Services fee includes a fee for the Project Architect’s Design Services in the amount of $ .
24.2.2 24.2.3 The Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager the Design/Build Contractor shall allocate the Pre- Pre-Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless the Owner and Construction Manager Design/Build Contractor agree otherwise.
Appears in 1 contract
Sources: Design/Build Agreement
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager Design/Build Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase Stage (Program5%) 05% $ . Schematic Design Stage (10% $ . %) Design Development Stage (20% %) $ . $ $ GMP Development Stage (20% %) $ . Construction Document Documents Stage (40% %) $ . Buyout Bid Proposal Stage 05% (5%) $ .Total $
24.2.2 The Owner may elect, at its option, to stage or “fast―fast-track” track‖ portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager the Design/Build Contractor shall allocate the Pre- Pre-Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless the Owner and Construction Manager Design/Build Contractor agree otherwise.
Appears in 1 contract
Sources: Design/Build Agreement
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager a Pre- Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase (Program) 05% $ . Schematic Design Stage 10% $ . Design Development Stage 20% $ . GMP Development Stage 20% $ . Construction Document Stage 40% $ . Buyout Stage 05% $ . Total Pre-Construction Phase Fee 100% $ .
24.2.2 Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, the Construction Manager shall allocate the Pre- Pre-Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless the Owner and Construction Manager agree otherwise.
Appears in 1 contract
Sources: Construction Manager Agreement
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager Design/Build Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase Stage (Program5%) 05% $ . Schematic Design Stage (10% %) $ . Design Development Stage (20% %) $ . GMP Development Stage (20% %) $ . Construction Document Documents Stage (40% %) $ . Buyout Bid Proposal Stage 05% (5%) $ .Total $
24.2.2 The Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager the Design/Build Contractor shall allocate the Pre- Pre-Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless the Owner and Construction Manager Design/Build Contractor agree otherwise.
Appears in 1 contract
Sources: Design/Build Agreement
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager a Pre- Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase (Program) 050% $ . Schematic Design Stage 100% $ . Design Development Stage 20% $ . GMP Development Stage 2025% $ . Construction Document Stage 4050% $ . Buyout Stage 05% $ .
24.2.2 Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager shall allocate the Pre- Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless Owner and Construction Manager agree otherwise.
Appears in 1 contract
Sources: Construction Manager Agreement
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager a Pre- Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase (Program) 05% $ . Schematic Design Stage 10% $ . Design Development Stage 20% $ . GMP Development Stage 20% $ . Construction Document Stage 40% $ . Buyout Stage 05% $ . Total Pre-Construction Phase Fee 100% $ .
24.2.2 Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager shall allocate the Pre- Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless Owner and Construction Manager agree otherwise.
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager a Pre- Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase (Program) 05% $ . $2,525,000.00 Schematic Design Stage 10% $ . $5.050.000.00 Design Development Stage 20% $ . $10,100,000.00 GMP Development Stage 20% $ . $10,100,000.00 Construction Document Stage 40% $ . $20,200,000.00 Buyout Stage 05% $ .$2,525,000.00
24.2.2 Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager shall allocate the Pre- Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless Owner and Construction Manager agree otherwise.
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. 24.2.1 For Pre-Construction Phase Services, Owner shall pay Construction Manager Design/Build Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount in accordance with the following schedule:: Phase or Stage % Amount Pre-Design Phase Stage (Program5%) 05% $ . Schematic Design Stage (10% %) $ . Design Development Stage (20% %) $ . GMP Development Stage (20% %) $ . Construction Document Documents Stage (40% %) $ . Buyout Stage 05% (5%) $ Total $
24.2.2 The Pre-Construction Phase Services fee includes a fee for the Project Architect’s Design Services in the amount of $ .
24.2.2 24.2.3 The Owner may elect, at its option, to stage or “fast-track” portions of the work. If Owner elects to implement the Project in multiple stages, Construction Manager the Design/Build Contractor shall allocate the Pre- Pre-Construction Phase Fee across all stages of the Project pursuant to the schedule set forth above, unless the Owner and Construction Manager Design/Build Contractor agree otherwise.
Appears in 1 contract
Sources: Design/Build Agreement