PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Construction Phase Fee in the total stipulated amount of B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes; C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materials, Owner shall pay Contractor
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialssite utility/envelope investigations and deferred maintenance scope verification, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsSite Investigation and Utility Survey, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialssite investigations, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatementtest piers, work associated with existing (MEP equipmentpotholing, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsand hydrovac, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Construction Phase Fee in the total stipulated amount ofof One Hundred Seventy Thousand and no/100 Dollars ($170,000.00);
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatementprinting/ solicitation, work associated with geotechnical investigations and an allowance for a phasing study and investigation of existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsconditions, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materials, Owner shall pay ContractorContractor Dollars ($0.00).
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsNone, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsinvestigative services, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsSite Investigation, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph Subsection 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated coordination with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsthe City, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated site investigation and coordination with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsthe City, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing Hydro Excavation GPR (MEP equipment, piping systemsUtility Location) utility condition assessment, limited demolition associated with exposure of concealed materialsSelective Interior Demolition and Design Pull Planning, Owner shall pay Contractor
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatementgeotechnical investigations including potholing, work associated with existing (MEP equipmentadditional geotechnical borings and ground penetrating radar slab, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsand other items agreed to by the owner in writing, Owner shall pay Contractor:
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialssite discovery, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph Subsection 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialssite utility/envelope investigations and deferred maintenance scope verification, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with site investigation and existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsinvestigation, Owner shall pay Contractor
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph Subsection 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatementSteel Connection Design, work associated with existing (MEP equipmentSteel Fabricator Engineering, piping systems) utility condition assessmentMass Timber Engineering, limited demolition associated with exposure of concealed materialsDemolition, Environmental Assessments, Surveying, Potholing, and Utility Investigations, Owner shall pay Contractor
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatementSite Investigations, work associated with existing (MEP equipmentPrinting, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsand other items agreed to in writing, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materials, Owner shall pay ContractorContractor Dollars ($ ).
Appears in 1 contract
Sources: Construction Contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Pre- Construction Phase Fee for payment purposes;; (See attached List
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsReimbursables), Owner shall pay Contractor
Appears in 1 contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Allowance for Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialslocates / potholing and test pier, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Construction Phase Fee in the total stipulated amount ofof One Hundred-Fifteen Thousand and no/100 Dollars ($115,000.00);
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsto be determined per 10.2.2), Owner shall pay ContractorContractor (a to be determined cost plus a not to exceed 10% ▇▇▇▇-up per 10.2.4) Dollars ($ TBD ).
Appears in 1 contract
Sources: Construction Contract
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with locating existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsutilities, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatement, work associated with existing (MEP equipment, piping systems) utility condition assessment, limited demolition associated with exposure of concealed materialsTBD, Owner shall pay ContractorContractor Sum to be negotiated Dollars ($ TBD ).
Appears in 1 contract
Sources: Construction Management Agreement
PRE-CONSTRUCTION PHASE FEE. A. For Pre-Construction Phase Services, Owner shall pay Contractor a Pre- Pre-Construction Phase Fee in the total stipulated amount of
B. Refer to Paragraph 10.2.1 for the percentages of each stage of work within the Pre-Construction Phase Fee for payment purposes;
C. For Reimbursable Services for partial asbestos abatementprinting, work associated with existing (MEP equipmentgeotechnical investigations including potholing, piping systems) ground penetrating radar or other utility condition assessmentinvestigation techniques, limited demolition associated with exposure of concealed materialsand other items agreed to by the owner in writing, Owner shall pay Contractor
Appears in 1 contract
Sources: Construction Management Agreement