Power System Controls. 1. Install one (1) RTU at the Generating Facility to monitor typical generation elements such as MW, MVAR, terminal voltage and circuit breaker status for the Generating Facility and plant auxiliary load, and transmit the information received thereby to the Distribution Provider’s grid control center. Notwithstanding that the RTU will be located on the Interconnection Customer’s side of the Point of Change of Ownership, the Distribution Provider shall own, operate and maintain the RTU as part of the Distribution Provider’s Interconnection Facilities. 2. Perform programming and in-service testing to add project to constraint management system including the addition of monitoring points.
Appears in 2 contracts
Sources: Generator Interconnection Agreement, Generator Interconnection Agreement