Notice of Dispute. If a dispute or difference arises between the Contractor and the Commonwealth or between the Contractor and the Contract Administrator in respect of any fact, matter or thing arising out of or in connection with the Contractor's Activities, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in clause 15. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 8 contracts
Samples: Formal Agreement, Formal Agreement, Formal Agreement
Notice of Dispute. If a dispute or difference arises between the Contractor and the Commonwealth Principal or between the Contractor and the Contract Administrator in respect of any fact, matter or thing arising out of of, or in connection with the Contractor's Activities, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in this clause 15. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 3 contracts
Samples: Commonwealth of Australia, Commonwealth of Australia, Commonwealth of Australia
Notice of Dispute. If a dispute or difference arises between the Contractor and the Commonwealth or between the Contractor and the Contract Administrator PDS Contractor in respect of any fact, matter or thing arising out of or in connection with the Contractor's Activities, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in clause 15. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator PDS Contractor and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 2 contracts
Samples: Formal Agreement, Formal Agreement
Notice of Dispute. If a dispute or difference arises between the Contractor Consultant and the Commonwealth Principal or between the Contractor Consultant and the Contract Administrator in respect of any fact, matter or thing arising out of of, or in connection with with, the Contractor's ActivitiesServices, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in this clause 1511. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 2 contracts
Samples: Commonwealth of Australia, Commonwealth of Australia
Notice of Dispute. If a dispute or difference arises between the Contractor Consultant and the Commonwealth or between the Contractor Consultant and the Contract Administrator in respect of any fact, matter or thing arising out of or in connection with the Contractor's ActivitiesServices, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in clause 1513. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 2 contracts
Samples: Formal Agreement, Design Services Contract
Notice of Dispute. If a dispute or difference arises between the Contractor and the Commonwealth or between the Contractor and the Contract Administrator in respect of any fact, matter or thing arising out of or in connection with the Contractor's Activities, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in this clause 15. .. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 2 contracts
Samples: Formal Agreement, Medium Works Contract
Notice of Dispute. If a dispute or difference arises between the Contractor Consultant and the Commonwealth or between the Contractor Consultant and the Contract Administrator in respect of any fact, matter or thing arising out of or in connection with the Contractor's ActivitiesServices, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in clause 1512. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 1 contract
Samples: Design Services Contract
Notice of Dispute. If a dispute or difference arises between the Contractor and the Commonwealth or between the Contractor and the Contract Administrator in respect of any fact, matter or thing arising out of or in connection with the Contractor's Activities, the Remediation Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in clause 15. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 1 contract
Samples: Panel Agreement
Notice of Dispute. If a dispute or difference arises between the Contractor and the Commonwealth or between the Contractor and the Contract Administrator PDS Contractor in respect of any fact, matter or thing arising out of or in connection with the Contractor's Activities, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in clause 15. .. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator PDS Contractor and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 1 contract
Samples: Formal Agreement
Notice of Dispute. If a dispute or difference arises between the Contractor and the Commonwealth or between the Contractor and the Contract Administrator in respect of any fact, matter or thing arising out of of, or in any way in connection with with, the Contractor's Activities, the Works or the Contract, or either party's conduct before the Contract, the dispute or difference must be determined in accordance with the procedure in this clause 15. Where such a dispute or difference arises, either party may give a notice in writing to the Contract Administrator and the other party specifying: the dispute or difference; particulars of the party's reasons for being dissatisfied; and the position which the party believes is correct.
Appears in 1 contract