Monthly Schedule Updates. Each month, Contractor shall submit to County for its review an update of the Accepted Project Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and Contractor cannot agree, then Contractor shall use County’s assessment of actual progress to prepare the Schedule Update. Contractor ’s monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that Contractor has taken or proposes to take to overcome problems and recover from delays. Contractor shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County’s acceptance of the monthly Schedule Update, it shall become the current Accepted Project Schedule. Any request for an extension of the Contract Time must be based on the Accepted Project Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County’s obligation to make such progress payment to Contractor.
Appears in 1 contract
Sources: Contract
Monthly Schedule Updates. Each month, Contractor shall submit to County for its review an update of the Accepted Project Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and Contractor cannot agree, then Contractor shall use County’s assessment of actual progress to prepare the Schedule Update. County Contractor ’s monthly Schedule Update shall include:
: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that Contractor has taken or proposes to take to overcome problems and recover from delays. Contractor shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County’s acceptance of the monthly County Schedule Update, it shall become the current Accepted Project Schedule. Any request for an extension of the Contract Time must be based on the Accepted Project Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County’s obligation to make County such progress payment to Contractor.
Appears in 1 contract
Sources: Construction Contract