Monthly Schedule Updates Sample Clauses

POPULAR SAMPLE Copied 1 times
Monthly Schedule Updates. Each month, ▇▇▇▇ shall submit to Owner for its review an update of the Accepted Construction Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If Owner and ▇▇▇▇ cannot agree, then ▇▇▇▇ shall use Owner’s assessment of actual progress to prepare the Schedule Update. ▇▇▇▇’▇ monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that ▇▇▇▇ has taken or proposes to take to overcome problems and recover from delays. ▇▇▇▇ shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On Owner’s acceptance of the monthly Schedule Update, it shall become the current Accepted Construction Schedule. Any request for an extension of the Contract Time must be based on the Accepted Construction Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to Owner’s obligation to make such progress payment to ▇▇▇▇.
Monthly Schedule Updates. Each month, CM shall submit to County for its review an update of the Accepted Construction Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and CM cannot agree, then CM shall use County’s assessment of actual progress to prepare the Schedule Update. CM’s monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated CPM report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that CM has taken or proposes to take to overcome problems and recover from delays. CM shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County’s acceptance of the monthly Schedule Update, it shall become the current Accepted Construction Schedule. Any request for an extension of the Contract Time must be based on the Accepted Construction Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County’s obligation to make such progress payment to CM.
Monthly Schedule Updates. Each month, Contractor shall submit to County for its review an update of the Accepted Project Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and Contractor cannot agree, then Contractor shall use County’s assessment of actual progress to prepare the Schedule Update. Contractor ’s monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that Contractor has taken or proposes to take to overcome problems and recover from delays. Contractor shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County’s acceptance of the monthly Schedule Update, it shall become the current Accepted Project Schedule. Any request for an extension of the Contract Time must be based on the Accepted Project Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County’s obligation to make such progress payment to Contractor.
Monthly Schedule Updates. On the 15th day of each month, the Contractor shall submit a Monthly Schedule Update using the same software used to prepare the Baseline Schedule. The Engineer will not submit the Engineer’s Monthly Estimate specified in 7-3.2 for processing until the Monthly Schedule Update has been submitted. The schedule may be emailed to the Engineer or submitted on a CD with 2 printed color copies on 11-inch x 17-inch sheets. Should the update not reflect the actual progress of the Work, the update will be returned to the Contractor for inclusion of the changes on the next update. Updates shall conform to 6-1.1.2 and the following: 1) Actual start and completion dates versus the original accepted Baseline Schedule shall be illustrated. 2) Deviations in the progress and sequence of the Work shall be identified and supported by a detailed narrative justification. The updates shall include necessary remedies and revisions to recover delays to the schedule to meet the original Contract milestones. 3) The data date shall be the 15th day of each month. 4) Change Order work scheduled after the Data Date that includes an approved time extension shall be shown as a Critical Path activity. Change Order work scheduled after the Data Date without an approved time extension shall be shown as a non- Critical Path activity. Change Order work performed prior to the Data Date shall be shown as an as-built activity. 5) The Required Completion Date milestone constraint date shall be adjusted to account for time extensions approved as of the Data Date. 6) The Scheduled Completion Date milestone constraint date shall be adjusted to match the Required Completion Date as of the Data Date. 7) Schedule updates shall only include changes related to a Time Impact Analysis (TIA) that has been accepted by the Engineer. Schedule updates shall not include changes related to a rejected TIA, or a TIA that is pending.
Monthly Schedule Updates. The Progressive Contractor shall prepare and deliver each Monthly Schedule Update with every Monthly Progress Payment Request. For avoidance of doubt, Monthly Schedule Updates do not serve to revise or amend, nor shall be deemed to revise or amend, a Baseline Pricing Package Schedule.
Monthly Schedule Updates. Each month, D-BE shall submit to OWNER for its review an update of the Accepted Project Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If OWNER and D-BE cannot agree, then D-BE shall use OWNER’s assessment of actual progress to prepare the Schedule Update. D-BE’s monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that D- BE has taken or proposes to take to overcome problems and recover from delays. D-BE shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On OWNER’s acceptance of the monthly Schedule Update, it shall become the current Accepted Project Schedule. Any request for an extension of the Contract Time must be based on the Accepted Project Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to OWNER’s obligation to make such progress payment to D-BE.