Monthly Schedule Updates Sample Clauses

Monthly Schedule Updates. Each month, XXXX shall submit to Owner for its review an update of the Accepted Construction Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If Owner and XXXX cannot agree, then XXXX shall use Owner’s assessment of actual progress to prepare the Schedule Update. XXXX’x monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that XXXX has taken or proposes to take to overcome problems and recover from delays. XXXX shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On Owner’s acceptance of the monthly Schedule Update, it shall become the current Accepted Construction Schedule. Any request for an extension of the Contract Time must be based on the Accepted Construction Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to Owner’s obligation to make such progress payment to XXXX.
AutoNDA by SimpleDocs
Monthly Schedule Updates. Each month, CM shall submit to County for its review an update of the Accepted Construction Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and CM cannot agree, then CM shall use County’s assessment of actual progress to prepare the Schedule Update. CM’s monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated CPM report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that CM has taken or proposes to take to overcome problems and recover from delays. CM shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County’s acceptance of the monthly Schedule Update, it shall become the current Accepted Construction Schedule. Any request for an extension of the Contract Time must be based on the Accepted Construction Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County’s obligation to make such progress payment to CM.
Monthly Schedule Updates. Each month, Contractor shall submit to County for its review an update of the Accepted Project Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and Contractor cannot agree, then Contractor shall use County Contractor monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that Contractor has taken or proposes to take to overcome problems and recover from delays. Contractor shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County Schedule Update, it shall become the current Accepted Project Schedule. Any request for an extension of the Contract Time must be based on the Accepted Project Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County such progress payment to Contractor.
Monthly Schedule Updates. The Progressive Contractor shall prepare and deliver each Monthly Schedule Update with every Monthly Progress Payment Request. For avoidance of doubt, Monthly Schedule Updates do not serve to revise or amend, nor shall be deemed to revise or amend, a Baseline Pricing Package Schedule.
Monthly Schedule Updates. On the 15th day of each month, the Contractor shall submit a Monthly Schedule Update using the same software used to prepare the Baseline Schedule. The Engineer will not submit the Engineer’s Monthly Estimate specified in 7-3.2 for processing until the Monthly Schedule Update has been submitted. The schedule may be emailed to the Engineer or submitted on a CD with 2 printed color copies on 11-inch x 17-inch sheets. Should the update not reflect the actual progress of the Work, the update will be returned to the Contractor for inclusion of the changes on the next update. Updates shall conform to 6-1.1.2 and the following:

Related to Monthly Schedule Updates

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Delivery Schedule The scheduled months of delivery of the Aircraft are listed in the attached Table 1. Exhibit B describes certain responsibilities for both Customer and Boeing in order to accomplish the delivery of the Aircraft.

  • Software Updates XXXXX agrees to keep current with software licensed from Skyward and will install new versions on a timeline approved by XXXXX governance. This timeline will be communicated by NWRDC to the Districts. School District Workstations Configuration requirements for devices and their software that school district personnel use to access WSIPC’s software modules can be found on our website: xxxxx://xxx.xxxxx.xxx/technology‐team/. State Reports XXXXX will provide, at no additional fee, all data reports required by the state that impact 50% or more of the school districts in the state. WSIPC and NWRDC will work with state agencies to gather requirements on the required data. WSIPC will inform NWRDC staff of any mandated changes to state reports and NWRDC will communicate the information to the District. Appendix B NWRDC FTE Fees Fiscal Only NWRDC Software Support Services XXXXX Software Licensing Total FTE Fee $13.63 $20.34 $33.97 $15.56 $13.08 $28.64 $24.52 $20.34 $44.86 Student Only Full Service

  • Pay Schedule 48.1 The regularly scheduled payday shall be bi-weekly, every other Thursday.

Time is Money Join Law Insider Premium to draft better contracts faster.