Mitigation Measures. The Contractor has taken, and continues to take, all reasonable measures, including those, if any, recommended by the Owner to minimize the impact of the delay on the Contract Schedule, and in the case of a claim for adjustment of the Contract Price, all reasonable measures, including those, if any, recommended by the Owner, to minimize the costs incurred, or anticipated to be incurred, by the Contractor as a result of the delay;
Appears in 3 contracts
Sources: Contracting Services Agreement, Form of Agreement, Consultant Agreement