Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and IO, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies. (b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IO's use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Services. (c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies. (d) IO may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOHRRH, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IO's HRRH’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) IO HRRH may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment and Existing Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOCAMH, shall, within 15 Business Days of Project Co's applicationthe Substantial Completion Notice, prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IO's CAMH’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) IO CAMH may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOMHCP, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IO's MHCP’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List in relation to the Substantial Completion Notice before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are such Minor Deficiencies.
(d) IO MHCP may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOSJHC, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IO's SJHC’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List in relation to the Substantial Completion Notice before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are such Minor Deficiencies.
(d) IO SJHC may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and IOWGH, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IOWGH's use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) IO WGH may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOHHS, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IO's HHS’ use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) IO HHS may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment and Existing Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IO, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IO's ’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) IO may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Procured Equipment or Existing Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Sources: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOHMQ, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of IOHMQ's and MAG’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the MCSCS Courthouse Activities and the HMQ FM Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) IO HMQ may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co EquipmentFF&E, and the failure to meet any such requirement shall constitute a Minor Deficiency.