Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance Committee, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include: (a) preventive maintenance schedule; (b) arrangements and procedures for carrying out urgent repairs; (c) criteria to be adopted for deciding maintenance needs; (d) intervals and procedures for carrying out inspection of all elements of the Bus Terminal; (e) intervals at which the Concessionaire shall carry out periodic maintenance; (f) arrangements and procedures for carrying out safety related measures; and (g) intervals for major maintenance works and the scope thereof. 17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements. 17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 16 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus Terminal;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 16 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus Terminal;; from
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 9 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no Not later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 4 contracts
Sources: Model Concession Agreement, Model Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 18.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority MOR and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalRail System;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and;
(g) intervals for major maintenance works and the scope thereof; and
(h) intervals of carrying out intermediate and periodic overhaul of track, signalling and communication system, and Traction System.
17.4.2 18.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 18.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 18.4.1 and 17.4.2 18.4.2 shall apply mutatis mutandis to such modifications.
Appears in 4 contracts
Sources: Construction Agreement, Construction Agreement, Construction Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) later than days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Concessioning Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 4 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalPort;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may may, modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses Clause 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 3 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority MOR and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalRail System;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and;
(g) intervals for major maintenance works and the scope thereof; and
(h) intervals of carrying out intermediate and periodic overhaul of track, signalling and communication system, and Traction System.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 3 contracts
Sources: Construction Contract, Construction Agreement, Construction Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety RequirementsRequirements as per Specifications and Standards. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalXXX Ropeway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 3 contracts
Sources: Model Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no 16.4.1 Not later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeMonitor[s], its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Service Requirements, Service Quality Manual, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 16.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Monitor[s] shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Service Requirements and Maintenance Requirements, Service Quality Manual, Maintenance Manual and Safety Requirements.
17.4.3 16.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 16.4.1 and 17.4.2 16.4.2 shall apply mutatis mutandis to such modifications.
Appears in 3 contracts
Sources: Public Private Partnership Agreement, Public Private Partnership Agreement, Public Private Partnership Agreement
Maintenance Programme. 17.4.1 On or before Final COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeExpert, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. , Such Maintenance Programme shall include:;
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; , and
(g) intervals for major maintenance works and the scope thereof.
(h) Routine maintenance schedule;
(i) Frequency of carrying out intermediate and periodic overhaul of the equipment
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Authority/ Independent Engineer/ Maintenance Committee Expert (as the case may be) shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 3 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 3 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus Terminal;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.. Downloaded from
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
(h) lane closure schedule for each type of maintenance (length and time)
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance Committee, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all components/ elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Supervision Committee shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no Not later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Project Bus TerminalPort;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority Government and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority MPRDC and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
(h) lane closure schedule for each type of maintenance (length and time)
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 15.3.1. On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire SPD shall provide to the Authority Railways and the Independent Engineer/ Maintenance CommitteeRailway Electrical Engineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalSolar Rooftop Power System;
(e) intervals at which the Concessionaire SPD shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and;
(g) intervals for major maintenance works and the scope thereof.; and
17.4.2 15.3.2. Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Railway Electrical Engineer shall review the same and convey its comments to the Concessionaire SPD with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 15.3.3. The Concessionaire SPD may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 15.4.1 and 17.4.2 15.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Power Purchase Agreement (Ppa), Power Purchase Agreement
Maintenance Programme. 17.4.1 16.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) later than days prior to the beginning of each Accounting Year during the Operation Concession Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer(s), its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive Preventive maintenance schedule;
(b) arrangements Arrangements and procedures for carrying out urgent repairsrepairs and regular wear & tear of the equipment installed by the Concessionaire;
(c) criteria Criteria to be adopted for deciding maintenance needs;
(d) intervals Intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals Intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements Arrangements and procedures for carrying out safety related measures; and
(g) intervals Intervals for major maintenance works and the scope thereof.
17.4.2 16.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer(s) shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 16.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 Articles 16.4.1 and 17.4.2 16.4.2 shall apply mutatis mutandis to such modifications.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Maintenance Programme. 17.4.1 15.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) later than days prior to the beginning of each Accounting Year during the Operation Concession Period, as the case may be, the Concessionaire shall provide to the Authority Government and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "" Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent major/ minor repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 15.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 15.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 Clause 15.4.1 and 17.4.2 15.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeExpert, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalStorage Facility;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and;
(g) intervals for major maintenance works and the scope thereof.; and
17.4.2 Within 15 (fifteenh) days frequency of receipt carrying out intermediate and periodic overhaul of the Maintenance Programme, the Independent Engineer/ Maintenance Committee shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify equipment. Provided that the Maintenance Programme as may be reasonable in shall not schedule any closure or overhaul at any time during the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modificationsHarvest Season.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no Not later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeAuthority, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) in respect of the MLCP and its components to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals Intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Authority shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses Articles 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus Terminal;; from
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.. Downloaded
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) later than days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeConcessioning Authority, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Concessioning Authority shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 17.5.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Operation & Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject facilities;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 17.5.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Operation & Maintenance Manual and Safety Requirements.
17.4.3 17.5.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 Clauses
17.5.1 and 17.4.2 17.5.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Model Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority MOPIT and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalHeliport;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments it connects to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, . Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority MPRDC and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 15.4.1 On or before COD of Bus Terminal and no later than 45 (forty five) later than days prior to the beginning of each Accounting Year during the Operation Concession Period, as the case may be, the Concessionaire shall provide to the Authority Government and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "Maintenance Programme") to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent major/ minor repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject Highway;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 15.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 15.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 Clause 15.4.1 and 17.4.2 15.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no 16.4.1 Not later than 45 (forty five) [•] days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeMonitor[s], its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Service Requirements, Service Quality Manual, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 16.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Monitor[s] shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Service Requirements and Maintenance Requirements, Service Quality Manual, Maintenance Manual and Safety Requirements.
17.4.3 16.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 16.4.1 and 17.4.2 16.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Public Private Partnership Agreement
Maintenance Programme. 17.4.1 17.4.1. On or before COD of Bus Terminal for each Phase and no later than 45 (forty forty-five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeEngineer, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalAirport;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 17.4.2. Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Engineer shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 17.4.3. The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement
Maintenance Programme. 17.4.1 On or before COD of Bus Terminal and no Not later than 45 (forty five) days prior to the beginning of each Accounting Year during the Operation Period, as the case may be, the Concessionaire shall provide to the Authority and the Independent Engineer/ Maintenance CommitteeAuthority, its proposed annual programme of preventive, urgent and other scheduled maintenance (the "“Maintenance Programme"”) of the Sports Infrastructure Project to comply with the Maintenance Requirements, Maintenance Manual and Safety Requirements. Such Maintenance Programme shall include:
(a) preventive maintenance schedule;
(b) arrangements and procedures for carrying out urgent repairs;
(c) criteria to be adopted for deciding maintenance needs;
(d) intervals and procedures for carrying out inspection of all elements of the Bus TerminalProject;
(e) intervals at which the Concessionaire shall carry out periodic maintenance;
(f) arrangements and procedures for carrying out safety related measures; and
(g) intervals for major maintenance works and the scope thereof.
17.4.2 Within 15 (fifteen) days of receipt of the Maintenance Programme, the Independent Engineer/ Maintenance Committee Authority shall review the same and convey its comments to the Concessionaire with particular reference to its conformity with the Maintenance Requirements, Maintenance Manual and Safety Requirements.
17.4.3 The Concessionaire may modify the Maintenance Programme as may be reasonable in the circumstances, and the procedure specified in Clauses Articles 17.4.1 and 17.4.2 shall apply mutatis mutandis to such modifications.
Appears in 1 contract
Sources: Concession Agreement