Common use of Late Notice Actual Costs Claim Process Clause in Contracts

Late Notice Actual Costs Claim Process. Within 56 days (or such other period as the parties may agree) of receipt by Network Rail of a Late Notice Actual Costs Claim Notice, Network Rail shall notify the Train Operator that either: it agrees that the Late Notice Actual Costs Claim Trigger is satisfied and agrees to the amount of the Late Notice Actual Costs claimed by the Train Operator in the Late Notice Actual Costs Claim Notice, in which case Network Rail shall also pay such Late Notice Actual Costs to the Train Operator within 56 days of receipt by Network Rail of the relevant Late Notice Actual Costs Claim Notice; or it agrees that the Late Notice Actual Costs Claim Trigger is satisfied but does not agree to the amount of the Late Notice Actual Costs claimed by the Train Operator in the Late Notice Actual Costs Claim Notice, in which case Network Rail shall: (if it has not already done so) commence negotiations with the Train Operator in respect of its Late Notice Actual Costs and shall continue such negotiations in good faith until they are concluded or until the Late Notice Actual Costs are determined in accordance with Clause 13; and pay to the Train Operator its Late Notice Actual Costs within 28 days of those Late Notice Actual Costs being agreed or determined in accordance with Clause 13 (as the case may be); or it does not agree that the Late Notice Actual Costs Claim Trigger is satisfied, in which case the matter shall be immediately referred for determination in accordance with Clause 13, and if it is determined in accordance with Clause 13 that the Late Notice Actual Costs Claim Trigger is satisfied then Network Rail shall: (if it has not already done so) commence negotiations with the Train Operator in respect of its Late Notice Actual Costs and shall continue such negotiations in good faith until they are concluded or until the Late Notice Actual Costs are determined in accordance with Clause 13; and pay to the Train Operator such Late Notice Actual Costs within 28 days of those Late Notice Actual Costs being agreed or determined in accordance with Clause 13 (as the case may be).

Appears in 2 contracts

Samples: www.orr.gov.uk, www.orr.gov.uk

AutoNDA by SimpleDocs

Late Notice Actual Costs Claim Process. Within 56 days (or such other period as the parties may agree) of receipt by Network Rail the CVL IM of a Late Notice Actual Costs Claim Notice, Network Rail the CVL IM shall notify the Train Operator that either: it agrees that the Late Notice Actual Costs Claim Trigger is satisfied and agrees to the amount of the Late Notice Actual Costs claimed by the Train Operator in the Late Notice Actual Costs Claim Notice, in which case Network Rail the CVL IM shall also pay such Late Notice Actual Costs to the Train Operator within 56 days of receipt by Network Rail the CVL IM of the relevant Late Notice Actual Costs Claim Notice; or it agrees that the Late Notice Actual Costs Claim Trigger is satisfied but does not agree to the amount of the Late Notice Actual Costs claimed by the Train Operator in the Late Notice Actual Costs Claim Notice, in which case Network Rail the CVL IM shall: (if it has not already done so) commence negotiations with the Train Operator in respect of its Late Notice Actual Costs and shall continue such negotiations in good faith until they are concluded or until the Late Notice Actual Costs are determined in accordance with Clause 13; and pay to the Train Operator its Late Notice Actual Costs within 28 days of those Late Notice Actual Costs being agreed or determined in accordance with Clause 13 (as the case may be); or it does not agree that the Late Notice Actual Costs Claim Trigger is satisfied, in which case the matter shall be immediately referred for determination in accordance with Clause 13, and if it is determined in accordance with Clause 13 that the Late Notice Actual Costs Claim Trigger is satisfied then Network Rail the CVL IM shall: (if it has not already done so) commence negotiations with the Train Operator in respect of its Late Notice Actual Costs and shall continue such negotiations in good faith until they are concluded or until the Late Notice Actual Costs are determined in accordance with Clause 13; and pay to the Train Operator such Late Notice Actual Costs within 28 days of those Late Notice Actual Costs being agreed or determined in accordance with Clause 13 (as the case may be).

Appears in 2 contracts

Samples: tfwrail.wales, tfwrail.wales

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.