Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Provider’s Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 16 contracts
Samples: Interconnection Agreement, Service Agreement, Clustering Large Generator Interconnection
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution ProviderParticipating TO’s Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 16 contracts
Samples: Standard Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Small Generator Interconnection Agreement
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution ProviderAffected Participating TO’s Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Samples: Facilities Agreement
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Participating TO’sDistribution Provider’s Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Samples: Limitations of Agreement
Interconnection Facilities Completion Date. The date upon which the construction of the new Distribution Provider’s Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Samples: Generator Interconnection Agreement
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Provider’s New Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Samples: Generator Interconnection Agreement
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Provider’s Phase 1 Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Provider’s Customer-Financed Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Samples: Service Agreement
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Provider’s Interconnection Facilities is complete and such facilities are successfully tested and ready for service. The Interconnection Facilities Completion Date for existing Distribution Provider’s Interconnection Facilities previously installed under the IFA as identified in Section 1(b)(i) is deemed to be the Effective Date of this GIA.
Appears in 1 contract
Samples: Generator Interconnection Agreement
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Provider’s Interconnection Facilities Facilities, excluding the Brea-Recycle 66kV Generation Tie-Line, is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Samples: California Edison Company
Interconnection Facilities Completion Date. The date upon which the construction of the Distribution Provider’s New Interconnection Facilities is complete and such facilities are successfully tested and ready for service.
Appears in 1 contract
Samples: Generator Interconnection Agreement