Installation Work. a) The Power Producer will cause the Project to be designed, manufactured, supplied, engineered, erected, tested and commissioned, operated & maintained and constructed substantially in accordance with RFS No SECI/Cont./77/2015 dated: 09-09-2015) and the sanction letter issued by SECI. The Power Producer shall provide to the Purchaser a bill of materials listing the major equipment constituting the System. Such bill of materials shall be provided within 30 days of the Commercial Operation Date. b) The Power Producer shall have access as reasonably permitted by the Purchaser to perform the Installation Work at the Premises in a manner that minimizes inconvenience to and interference with the use of the Premises to the extent commercially practical. c) It is agreed between the Parties that the Power Producer shall commission the System with a capacity of KWp. Power Producer may construct a System of smaller size if it receives only part approval of government subsidies or for any other material commercial reason, as mutually agreed between the Parties in writing, In the event a System of smaller capacity is eventually agreed to be installed, the clauses pertaining to Purchase Price as set out under this Agreement shall be adjusted proportionately as per mutual agreement between the Parties in writing. d) The Power Producer shall provide and lay the dedicated electrical cables for transmission of Solar Power from the System up to the Delivery Point. Transmission or distribution of Solar Power beyond this point will be the responsibility of the Purchaser. The Delivery Point shall be where the Main Metering System is located. e) Unless otherwise agreed between the Parties, the Power Producer shall not do (a) chipping of rooftop; or (b) water proofing of roof to be disturbed
Appears in 1 contract
Sources: Power Purchase Agreement
Installation Work. a) The Power Producer will cause the Project to be designed, manufactured, ,supplied, engineered, erected, tested and commissioned, operated & &maintained and constructed substantially in accordance with RFS No SECI/Cont./77/2015 dated: 09-09-2015) _ and the sanction letter issued by SECI<NAME OFEXPERT PSU>. The Power Producer shall provide to the Purchaser a bill of materials ▇▇▇▇ ofmaterials listing the major equipment constituting the System. Such bill of materials ▇▇▇▇ ofmaterials shall be provided within 30 days of the Commercial Operation DateOperationDate.
b) The Power Producer shall have access as reasonably permitted by the Purchaser thePurchaser to perform the Installation Work at the Premises in a manner that minimizes thatminimizes inconvenience to and interference with the use of the Premises to the tothe extent commercially practical.
c) It is agreed between the Parties that the Power Producer shall commission the System theSystem with a capacity of KWpkWp. Power Producer may construct a System of Systemof smaller size if it receives only part approval of government subsidies or for any forany other material commercial reason, as mutually agreed between the Parties in Partiesin writing, In the event a System of smaller capacity is eventually agreed to be installedbeinstalled, the clauses pertaining to Purchase Price as set out under this Agreement thisAgreement shall be adjusted proportionately as per mutual agreement between the betweenthe Parties in writing.
d) The Power Producer shall provide and lay the dedicated electrical cables for transmission fortransmission of Solar Power from the System up to the Delivery Point. .Transmission or distribution of Solar Power beyond this point will be the responsibility theresponsibility of the Purchaser. The Delivery Point shall be where the Main Metering MainMetering System is located.
e) Unless otherwise agreed between the Parties, the Power Producer shall not do (ado(a) chipping of rooftop; or (b) water proofing of roof to be disturbeddisturbed ;(
Appears in 1 contract
Sources: Power Purchase Agreement (Ppa)
Installation Work. a) The Power Producer will cause the Project to be designed, manufactured, supplied, engineered, erected, tested and commissioned, operated & maintained and constructed substantially in accordance with RFS No SECI/Cont./77/2015 dated: 09-09-2015Cont./01/2016/500 dated:22/04/2016) and the sanction letter issued by SECI. The Power Producer shall provide to the Purchaser a bill of materials listing the major equipment constituting the System. Such bill of materials shall be provided within 30 days of the Commercial Operation Date.
b) The Power Producer shall have access as reasonably permitted by the Purchaser to perform the Installation Work at the Premises in a manner that minimizes inconvenience to and interference with the use of the Premises to the extent commercially practical.
c) It is agreed between the Parties that the Power Producer shall commission the System with a capacity of KWp. Power Producer may construct a System of smaller size if it receives only part approval of government subsidies or for any other material commercial reason, as mutually agreed between the Parties in writing, In the event a System of smaller capacity is eventually agreed to be installed, the clauses pertaining to Purchase Price as set out under this Agreement shall be adjusted proportionately as per mutual agreement between the Parties in writing.
d) The Power Producer shall provide and lay the dedicated electrical cables for transmission of Solar Power from the System up to the Delivery Point. Transmission or distribution of Solar Power beyond this point will be the responsibility of the Purchaser. The Delivery Point shall be where the Main Metering System is located.
e) Unless otherwise agreed between the Parties, the Power Producer shall not do (a) chipping of rooftop; or (b) water proofing of roof to be disturbed
Appears in 1 contract
Sources: Power Purchase Agreement