Common use of Individual Test Reports Clause in Contracts

Individual Test Reports. After Contractor has completed any Performance Test, it shall provide to Owner a preliminary test report for each such test as soon as reasonably practicable but in no event more than 24 hours after the completion of such test (or as soon thereafter as such reports are first available to Contractor) providing a summary of such test and including all raw data taken during such test and, if Contractor believes such test has been passed, a final test report within 30 days thereafter. If Contractor believes such test has been passed, Contractor shall include sufficient results of such testing in the preliminary test report to allow Owner to determine that there is a high probability that the final test results will confirm that such test has been passed. Contractor shall not be required to provide an individual test report (preliminary or final) pursuant to this Section 7.3.3 if the results of such test are, at the same time, to be included in the reports to be provided by Contractor pursuant to Section 7.3.1 or Section 7.3.2.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction Agreement (Ada-Es Inc), Engineering, Procurement and Construction Agreement (Ada-Es Inc)

Individual Test Reports. After Contractor has completed any Performance Test, it shall provide to Owner a preliminary test report for each such test as soon as reasonably practicable but in no event more than that 24 hours after the completion of such test (or as soon thereafter as such reports are first available to Contractor) providing a summary of such test and including all raw data taken during such test and, if Contractor believes such test has been passed, a final test report within 30 days thereafter. If Contractor believes such test has been passed, Contractor shall include sufficient results of such testing in the preliminary test report to allow Owner to determine that there is a high probability that the final test results will confirm that such test has been passed. Contractor shall not be required to provide an individual test report (preliminary or final) pursuant to this Section 7.3.3 if the results of such test are, at the same time, to be included in the reports to be provided by Contractor pursuant to Section 7.3.1 or Section 7.3.27.3.1.

Appears in 1 contract

Sources: Engineering, Procurement and Construction Agreement (Ada-Es Inc)