Common use of Guaranteed Commercial Operation Clause in Contracts

Guaranteed Commercial Operation. (a) Seller shall cause the Project to achieve the Commercial Operation Date by the Guaranteed Commercial Operation Date, as such date may be extended in accordance with Section 4.3(c). (b) If Seller believes that the requirements for Commercial Operation have been satisfied and fulfilled, Seller shall present to Buyer, an independent engineer's report, the form of which is attached as Exhibit L, verifying that each of the conditions set forth therein has been satisfied or waived in writing by both Parties. The date identified in such report as the day Commercial Operation was achieved shall be the Commercial Operation Date in the absence of manifest error. (c) Permitted Extensions to the Guaranteed Commercial Operation Date are as follows, provided that the Permitted Extensions shall not exceed one hundred eighty (180) days: (i) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days if from the Effective Date Seller has used Commercially Reasonable Efforts to have the Project physically interconnected to the Transmission Provider’s Transmission System and to complete all Electric Interconnection Upgrades, if any, but such Electric Interconnection Upgrades cannot be completed thirty (30) days prior to the Guaranteed Commercial Operation Date. Seller shall provide Buyer Notice of such occurrence promptly upon the determination that such physical interconnection or upgrades cannot be completed timely in accordance with the Interim Milestones schedule set forth in Exhibit J, and Seller shall work diligently to resolve the delay (“Transmission Delay”); (ii) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days if from the Effective Date Seller has used Commercially Reasonable Efforts to obtain the Governmental Approvals necessary for the construction and operation of the Project, but is unable to obtain such Governmental Approvals by the deadline date therefor in the Interim Milestones schedule set forth in Exhibit J, and Seller has worked diligently to resolve the delay (“Permitting Delay”); and (iii) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days for Force Majeure Events (“Force Majeure Extension”); provided, that Seller works diligently to resolve the effect of the Force Majeure Event and provides evidence of its efforts promptly to Buyer upon Buyer’s written request. (d) Notwithstanding the foregoing, if Seller claims more than one Permitted Extension under Section 4.3(c), such extensions cannot cumulatively exceed one hundred eighty (180) days and all Permitted Extensions taken shall be concurrent, rather than cumulative, during any overlapping days. (e) If Seller claims a Permitted Extension, Seller shall provide prompt Notice to Buyer of the occurrence of the event causing delay and the anticipated delay impact, which Notice must clearly identify the Permitted Extension being claimed and include information necessary for Buyer to verify the length and qualification of the extension.

Appears in 1 contract

Sources: Power Sales Contract

Guaranteed Commercial Operation. (a) Seller shall cause the Project to achieve the Commercial Operation Date by the Guaranteed Commercial Operation Date, as such date may be unless the Guaranteed Commercial Operation Date is extended in accordance with Section 4.3(c). (b) If Seller believes that the requirements for Commercial Operation have been satisfied and fulfilled, Seller shall present to Buyer, an independent engineer's report, the form of which is attached as Exhibit L, verifying that each of the conditions set forth therein has been satisfied or waived in writing by both Parties. The date identified in such report as the day Commercial Operation was achieved shall be the Commercial Operation Date in the absence of manifest error. (c) Permitted Extensions to the Guaranteed Commercial Operation Date are as follows, provided that the Permitted Extensions shall not exceed one hundred eighty (180) days: (i) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred and eighty (180) days if from the Effective Date Seller has used Commercially Reasonable Efforts to have the Project physically interconnected to the Transmission Provider’s Transmission System and to complete all Electric Interconnection Upgrades, if any, but such interconnection or Electric Interconnection Upgrades cannot be completed thirty (30) days prior to the Guaranteed Commercial Operation Date. Seller shall provide Buyer Notice of such occurrence promptly upon the determination that such physical interconnection or upgrades cannot be completed timely in accordance with the Interim Milestones schedule set forth in Exhibit J, Milestone Schedule and Seller shall work diligently to resolve the delay (“Transmission Delay”); (ii) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days if from the Effective Date Seller has used Commercially Reasonable Efforts to obtain the Governmental Approvals necessary for the construction and operation of the Project, but is unable to obtain such Governmental Approvals by the deadline date therefor in the Interim Milestones schedule set forth in Exhibit J, Milestone Schedule and Seller has worked diligently to resolve the delay (“Permitting Delay”); and (iii) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days for Force Majeure Events (“Force Majeure Extension”); provided, provided that Seller works diligently to resolve the effect of the Force Majeure Event and provides evidence of its efforts promptly to Buyer upon Buyer▇▇▇▇▇’s written request. (d) Notwithstanding the foregoing, if Seller claims more than one Permitted Extension under Section 4.3(c), such extensions cannot cumulatively exceed one hundred eighty (180) days and all Permitted Extensions taken shall be concurrent, rather than cumulative, during any overlapping days. (e) If Seller claims a Permitted Extension, Seller shall provide prompt Notice to Buyer of the occurrence of the event causing delay and the anticipated delay impact, which Notice must clearly identify the Permitted Extension being claimed and include information necessary for Buyer to verify the length and qualification of the extension.

Appears in 1 contract

Sources: Solar Project Power Sales Contract