Guaranteed Commercial Operation Clause Samples

The Guaranteed Commercial Operation clause sets a specific deadline by which a project, typically in the energy or infrastructure sector, must achieve full operational status as defined in the contract. This clause outlines the criteria that constitute commercial operation, such as meeting performance standards or passing required tests, and may specify remedies or penalties if the deadline is not met. Its core function is to ensure timely project completion and provide certainty to all parties regarding when the project will begin generating revenue or fulfilling its intended purpose.
Guaranteed Commercial Operation. Seller shall cause the Project to achieve the Commercial Operation Date by the Guaranteed Commercial Operation Date, unless extended in accordance with Section 3.9(c)(ii). Extensions. The Guaranteed Commercial Operation Date may be extended one time for no more than a six (6) month period (the “Project Cure Period”) for cumulative delays if Seller demonstrates to Buyer’s reasonable satisfaction after giving written notice as soon as reasonably possible but at least at sixty (60) days prior to the original Guaranteed Commercial Operation Date, which includes a feasible remedial action plan, if any of the following have occurred:
Guaranteed Commercial Operation. (a) Seller shall cause the Project to achieve the Commercial Operation Date by the Guaranteed Commercial Operation Date, as such date may be extended in accordance with Section 4.3(c). (b) If Seller believes that the requirements for Commercial Operation have been satisfied and fulfilled, Seller shall present to Buyer, an independent engineer's report, the form of which is attached as Exhibit L, verifying that each of the conditions set forth therein has been satisfied or waived in writing by both Parties. The date identified in such report as the day Commercial Operation was achieved shall be the Commercial Operation Date in the absence of manifest error. (c) Permitted Extensions to the Guaranteed Commercial Operation Date are as follows, provided that the Permitted Extensions shall not exceed one hundred eighty (180) days: (i) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days if from the Effective Date Seller has used Commercially Reasonable Efforts to have the Project physically interconnected to the Transmission Provider’s Transmission System and to complete all Electric Interconnection Upgrades, if any, but such Electric Interconnection Upgrades cannot be completed thirty (30) days prior to the Guaranteed Commercial Operation Date. Seller shall provide Buyer Notice of such occurrence promptly upon the determination that such physical interconnection or upgrades cannot be completed timely in accordance with the Interim Milestones schedule set forth in Exhibit J, and Seller shall work diligently to resolve the delay (“Transmission Delay”); (ii) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days if from the Effective Date Seller has used Commercially Reasonable Efforts to obtain the Governmental Approvals necessary for the construction and operation of the Project, but is unable to obtain such Governmental Approvals by the deadline date therefor in the Interim Milestones schedule set forth in Exhibit J, and Seller has worked diligently to resolve the delay (“Permitting Delay”); and (iii) The Guaranteed Commercial Operation Date may be extended on a day for day basis for a cumulative period equal to no more than one hundred eighty (180) days for Force Majeure Events (“Force Majeure Extension”); provided, that Seller works diligently to resolve the ...
Guaranteed Commercial Operation