Float Time. Show activities on their early dates with corresponding Total Float Time noted beside them. i. Project Schedule shall not include more than 40 calendar days of Float Time absent City approval.
Appears in 2 contracts
Float Time. Show activities on their early dates with corresponding Total Float Time noted beside them.
i. Project Schedule shall not include more than 40 calendar days of Float Time absent written City approval.
Appears in 1 contract