First Article Test Clause Samples
A First Article Test clause requires the supplier to produce an initial sample or batch of goods for inspection and approval before full-scale production begins. In practice, this means the buyer will evaluate the first completed unit or lot to ensure it meets all specified requirements, such as quality, design, and performance standards. This clause helps prevent large-scale production of non-conforming products by identifying and resolving issues early in the manufacturing process.
First Article Test. For the First Article Test (FAT), Components shall be subject to Tests as described in the Technical Specification. The FAT shall be performed at the Contractor’s facility in North America. Successful completion of FAT shall serve as the prerequisite for beginning production of the Deliverables under Test. The FAT shall be considered successfully completed when all Deliverables are Conforming Deliverables.
First Article Test. If SIEMENS chooses to perform a first article test upon the Products, then such test may be performed at TANISYS' premises before delivery of the first quantity shipment of each type or any modified version thereof and further deliveries shall be subject to successful performance of such test. Such tests shall be performed at no cost to SIEMENS by TANISYS and under the observation of the SIEMENS Quality Assurance representative where necessary.
First Article Test. For purposes of this contract, the first article test shall consist of:
a. The Logistics Demonstration (LD)
b. Production Verification Test (PVT)
c. Initial Operational Test and Evaluation (IOT&E)
First Article Test. 3.10.4.1 The Contractor shall perform a First Article Test (FAT) on one PPS and one MCP to demonstrate the built to print unit will pass testing. The test, test item and test objective are identified in the TDPs.
3.10.4.2 The Contractor shall prepare for all aspects of test planning, conduct and reporting, including, as a minimum, a test plan a test report, fixtures, support equipment and apparatus, instrumentation, test site, test equipment, personnel, safety and post-test asset disposition.
3.10.4.3 The Contractor shall convene a Test Readiness Review (TRR) at least five working days prior to each FAT event. Multiple FAT events may be reviewed during a single TRR. The TRR shall be chaired by the Contractor and co-chaired by the Government. Additional Government subject matter experts will attend each TRR.
3.10.4.4 The Government reserves the right to witness all FAT activities. The Contractor shall maintain a comprehensive schedule of FAT events that includes date, time, expected duration and location, and shall notify the Government at least five days prior to the first event.
3.10.4.5 The Contractor shall prepare a comprehensive test plan for the FAT unit. (CDRL A006)
3.10.4.6 The Contractor shall prepare a Quick Look Report after completion of a FAT event. The quick look report shall offer an initial assessment of the unit under test performance and shall describe all apparent anomalies. (CDRL A007)
3.10.4.7 The Contractor shall prepare a final report after the completion of the FAT event. (CDRL A008)
3.10.4.8 The Contractor shall coordinate testing of the Lowest Replaceable Unit (LRU) of the PPS and MCP with the Government. The Government has the Automated Test Equipment (ATE) to test the below LRUs:
First Article Test. If Fujitsu chooses to perform a first article test, such test will be performed at NetApp's point of manufacture or Fujitsu facility prior to the delivery of the first quantity shipment of each type or modified version of PRODUCTS. Future deliveries shall be subject to the successful passing of such test. Should the test be performed at NetApp's facility, it shall be conducted without charge to Fujitsu.
First Article Test