Final Payment Statement. 14.5.1 Within 60 (sixty) days after receiving the Completion Certificate the Contractor shall submit to the EIC for consideration six copies of a Final Payment Statement as per approved format by EIC/PMC (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the EIC/PMC: (a) the summary of Contractor’s interim Payment claims for Works as submitted in accordance with contract; (b) the amounts received from the RSCL against each claim; and (c) any further sums which the Contractor considers due to it from the RSCL. If the EIC/PMC disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the EIC/PMC may reasonably require. The EIC/PMC Engineer shall deliver to the RSCL:
Appears in 1 contract
Sources: General Conditions of Contract
Final Payment Statement. 14.5.1 14.4.1 Within 60 (sixty) days after receiving the Completion Certificate the Contractor shall submit to the EIC for consideration six copies of a Final Payment Statement as per approved format by EIC/PMC (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the EIC/PMC:
(a) the summary of Contractor’s interim Payment claims for Works as submitted in accordance with contract;
(b) the amounts received from the RSCL against each claim; and
(c) any further sums which the Contractor considers due to it from the RSCL. If the EIC/PMC disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the EIC/PMC may reasonably require. The EIC/PMC Engineer shall deliver to the RSCL:
Appears in 1 contract
Sources: General Conditions of Contract