Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
Appears in 1 contract
Sources: Construction Contract
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
Appears in 1 contract
Sources: Contract Agreement
Final Payment Statement. 19.13.1 Within 1Within 60 (sixty) days after of receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Authority Engineer for consideration six copies of a Final Payment Statement final payment statement (the “Final Payment Statement”) for Works), with supporting documents showing in detaildocuments, in the form prescribed by the Authority’s Authority Engineer:
Appears in 1 contract
Sources: Engineering, Procurement and Construction (Epc) Agreement