Final Contract Completion Sample Clauses
The Final Contract Completion clause defines the point at which all contractual obligations between the parties are considered fully satisfied. Typically, this clause outlines the requirements for completion, such as the delivery of all goods or services, final inspections, and the resolution of any outstanding issues or defects. By clearly establishing when the contract is officially complete, this clause helps prevent disputes over lingering responsibilities and provides both parties with certainty regarding the end of their obligations.
Final Contract Completion. 6.29.2.1 When all items on the A/E’s Punch List have been completed to the satisfaction of the A/E, all requirements of the Contract Documents have been completed, and the provisions of Sections 6.24 through 6.28 have been fulfilled, the A/E shall prepare and recommend execution of a final Certificate of Contract Completion.
6.29.2.2 The date that the Contracting Authority executes the final Certificate of Contract Completion is the date of Contract Completion.
Final Contract Completion. 6.29.2.1 When all items on the Contracting Authority’s Punch List have been completed to the satisfaction of the Contracting Authority, all requirements of the Contract Documents have been completed, and the provisions of Sections 6.24 through 6.28 have been fulfilled, the Contracting Authority shall prepare and issue a final Certificate of Contract Completion.
6.29.2.2 The date that the Contracting Authority executes the final Certificate of Contract Completion is the date of Contract Completion.
Final Contract Completion. 6.30.2.1 When all items on the A/E’s Punch List have been completed to the satisfaction of the A/E, all requirements of the Contract Documents have been completed, and the provisions of Sections 1.1 through 6.2829 have been fulfilled, the A/E shall prepare and recommend execution of a Final Certificationfinal Certificate of Contract Completion. Version Control Document
6.30.2.2 The date that the Contracting Authority executes the Final Certificationfinal Certificate of Contract Completion is the date that the Work of the Contract is accepted (“Final Acceptance”). If a Partial Certification of Contract Completion was not executed for the Contract, the date that the Contracting Authority executes the Final Certification of Contract Completion is the date that the Correction Period commences, and retained funds may be released. Final Acceptance is subject to Section 6.