Final Contract Completion. 6.29.2.1 When all items on the A/E’s Punch List have been completed to the satisfaction of the A/E, all requirements of the Contract Documents have been completed, and the provisions of Sections 6.24 through 6.28 have been fulfilled, the A/E shall prepare and recommend execution of a final Certificate of Contract Completion. 6.29.2.2 The date that the Contracting Authority executes the final Certificate of Contract Completion is the date of Contract Completion.
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Professional Services
Final Contract Completion. 6.29.2.1 31.2.1 When all items on the A/E’s Punch List have been completed to the satisfaction of the A/E, all requirements of the Contract Documents have been completed, and the provisions of Sections 6.24 6.246.25 through 6.28 6.286.29 have been fulfilled, the A/E shall prepare and recommend execution of a final Final Certificationfinal Certificate of Contract Completion.
6.29.2.2 The date that the Contracting Authority executes the final Certificate of Contract Completion is the date of Contract Completion.. Version Control Document
Appears in 2 contracts
Sources: General Contracting Agreement, Standard Requirements for Public Facility Construction
Final Contract Completion. 6.29.2.1 6.30.2.1 When all items on the A/E’s Punch List have been completed to the satisfaction of the A/E, all requirements of the Contract Documents have been completed, and the provisions of Sections 6.24 6.25 through 6.28 6.29 have been fulfilled, the A/E shall prepare and recommend execution of a final Certificate of Contract Completion.
6.29.2.2 6.30.2.2 The date that the Contracting Authority executes the final Certificate of Contract Completion is the date of Contract Completion.
Appears in 1 contract
Sources: Standard Requirements for Public Facility Construction